The UK’s A14 route is seeing a major upgrade

Work is progressing well on the project to upgrade the busy A14 route in the UK. A major milestone has been achieved with and important phase of the bridge installation having taken place. A 39m viaduct beam has been placed successfully for the bridge, which spans the River Ouse in Cambridgeshire. A key role in this work has been taken by the firm Cleveland Bridge UK. As part of Highways England’s £1.5 billion A14 Cambridge to Huntingdon improvement scheme, Cleveland Bridge was contracted by the A14 Integr
June 14, 2018 Read time: 2 mins
The A14 Viaduct being installed over the River Great Ouse
Work is progressing well on the project to upgrade the busy A14 route in the UK. A major milestone has been achieved with and important phase of the bridge installation having taken place. A 39m viaduct beam has been placed successfully for the bridge, which spans the River Ouse in Cambridgeshire.


A key role in this work has been taken by the firm Cleveland Bridge UK. As part of 8100 Highways England’s £1.5 billion A14 Cambridge to Huntingdon improvement scheme, Cleveland Bridge was contracted by the A14 Integrated Delivery Team (IDT) to design, fabricate and install a 750m viaduct bridge spanning the river and a large area of bordering flood plain on each bank.

Containing 6,000tonnes of steel and comprising 76 separate main girders and 800 cross girders, the structure was fabricated at Cleveland Bridge’s production facility in Darlington, County Durham before component parts were transported to site by road over a period of months. The majority of the main girders are 40m long, 2m deep and weigh 50tonnes.

The section of the bridge crossing the river has the longest span, so a complex series of girders has been installed to carry the weight of the greater load.

To enable the installation of the structure, including the most recent viaduct sections, a temporary platform was constructed under the length of the new bridge to provide a solid base for cranes and lorries.

However, to reduce time and site congestion, Cleveland Bridge utilised a 600tonne capacity crawler crane for the installation, which could lift all components for each section of the bridge from a single position at the side of the bridge. This meant fewer crane movements and no need to move the crane across the bridge footprint.

Chris Droogan, managing director of Cleveland Bridge UK, said: “The River Great Ouse viaduct is a showpiece element of the A14 project and is worthy of its place as one of Cleveland Bridge’s most significant structures in our history.”

“The viaduct will have a major impact on improving this part of the UK road network and we are very proud to have played a part in its development.”

For more information on companies in this article

Related Content

  • Airport preparation through compaction
    April 12, 2018
    Two major airport projects around the world are being constructed on poor ground and have required extensive compaction - Mike Woof writes With air travel continuing to increase around the world, airport capacity is being upgraded in many major cities. Two of the world’s largest mega cities, Beijing and Istanbul, are constructing new airports to cope with growing demand. This is because the existing facilities are simply unable to cope with projected growth for aviation and some of the airports are alrea
  • Complete control of machines using technology
    December 12, 2019
    Sophisticated machine control technology has been utilised on heavy equipment to help deliver a challenging project in New Zealand
  • AGD’s 318 Traffic Control Radar rises above the fray
    September 28, 2018
    England’s Staffordshire County has replaced speed detection loops at a busy junction with the AGD above-ground 318 Traffic Control Radar. The council, as with many local authorities, is avoiding in-ground detection wherever possible as a smart solution to wear-prone loops and magnetometers. “Because the road surface was in such poor condition where the [below-ground] loops would have been installed, the AGD 318 radar gave us an ideal, non-intrusive solution for detection,” said Martin Fenlon, principal si
  • Efficient earthmoving builds new road links
    February 7, 2012
    Efficient earthmoving is allowing productive road construction in the Egyptian desert, Mike Woof reports. Despite ferocious desert temperatures, efficient earthmoving operations will help build new road links in Southern Egypt. Close to the Egyptian city of Assuit, the contractor Orascom is working on three key desert highway projects that will provide vital transport connections for the country's growing economy.