UK’s A14 route to open early

Highways England has announced that the UK’s A14 route is to open early.
By MJ Woof February 11, 2020 Read time: 2 mins
The new A14 route will cut congestion along a vital transport corridor for the UK – image ©courtesy of Highways England

Highways England has announced that the new A14 dual carriageway upgrade in the UK will open in the second quarter of 2020, some six months ahead of schedule. The project has cost £1.5 billion to carry out and is designed to reduce delays for transport between the East of England and the Midlands.

The first 19km bypass section of the new 34km route opened in late 2019, one year ahead of schedule. This important route is vital for the UK’s transport needs and carries around 85,000 vehicles/day, including 21,000 heavy vehicles/day. The A14 connects ports in East England with the West Midlands, a key hub for industry and logistics.

The project has been carried out to reduce congestion and delays through this part of the UK and the new A14 section will improve traffic flow and capacity considerably. The work has been carried out by a joint venture; the A14 Integrated Delivery Team. This comprises Balfour Beatty, Costain and Skanska, and design consultants Atkins and CH2M.

The project has previously won four awards at the 2019 British Construction Industry Awards. The awards were: Digital Transformation Initiative of the Year; Productivity Initiative of the Year; Partnership Initiative of the Year; Initiative of the Year Award.

Construction activity commenced on the project in November 2016, and the work has employed around 13,000 people in all. The new link will operate as an A road trunk route, instead of a motorway as had been originally planned.

As well as the Huntingdon southern bypass, the project includes an upgrade to the A14 between Swavesey and Milton, and a new local access road, the A1307, which runs parallel to it between Cambridge and Godmanchester. In addition, 38km of new facilities for vulnerable road users have also been included in the overall scheme.

The spring opening date will mark the end of permanent roadworks and reduced speed limits on the new A14 and the A1307. However, the project team will still need to carry out landscaping, installing new traffic management technology, and work in the verges. Some temporary overnight closures or off-peak daytime lane closures will be needed.

Related Content

  • Temporary bridge replacement in the US
    July 2, 2019
    A temporary bridge structure provided by Acrow Bridge is maintaining traffic flow for a key crossing in Vermont. The bascule bridge is allowing both vehicular and vessel traffic to pass during the reconstruction work to the North Hero-Grand Isle Drawbridge in Vermont. The US$60 million project involves replacing the historic twin leaf bascule bridge on Lake Champlain. This modular steel bascule bridge is allowing transport to continue to and from the Lake Champlain island towns of North Hero and Grand Isl
  • Fast-track Biloxi Bay bridge
    July 18, 2012
    Construction of a bridge destroyed in a hurricane was completed early, and with some added aesthetic benefits Hurricane Katrina, one of the deadliest and costliest natural disasters in US history, made landfall on 29 August, 2005, devastating the Gulf Coast. The US 90 Bridge over Biloxi Bay (connecting the communities of Biloxi and Ocean Springs, Mississippi) was one of many major highway and railroad bridges knocked out of service due to extensive storm damage. The eye of the storm passed 96km west of Bilo
  • Norway halts E6 Storhove-Roterud near Lågen
    January 2, 2023
    Road agency Nye Veier received dispensation for construction of a motorway in the Lågen delta from the State Administrator last April but the work has run into environmental concerns
  • Argentina developing road infrastructure and road maintenance
    June 13, 2016
    Argentina has set out plans for a major refurbishment of much of its dilapidated road network. The work will take four years to complete and involves building 2,800km of highways as well as 4,000km of trunk roads. This is a substantial programme of works, which should also deliver around 35,000 much-needed jobs. The Ministry for Transport has drawn up the schedule work the programme, which is expected to cost in the region of US$14.43 billion. The country’s total road system stretches for some 182,000km