Tunnel breakthrough for new Auckland link in New Zealand

Auckland’s Western Ring Route project update - Mary Bell writes. A number of integrated projects in Auckland, New Zealand, will improve the lot of road users and cyclists, and significantly alter the topography of the city’s motorway. On September 29th the tunnel boring machine digging the first of twin road tunnels beneath the city broke into daylight after 10 months underground. The new 2.4km-long Waterview tunnels will connect the city’s Northwestern and Southwestern motorways, each carrying three lane
October 8, 2014 Read time: 4 mins
The breakthrough of the TBM is the latest stage in New Zealand’s Waterview project
Auckland’s Western Ring Route project update - Mary Bell writes

A number of integrated projects in Auckland, New Zealand, will improve the lot of road users and cyclists, and significantly alter the topography of the city’s motorway.

On September 29th the tunnel boring machine digging the first of twin road tunnels beneath the city broke into daylight after 10 months underground.

The new 2.4km-long Waterview tunnels will connect the city’s Northwestern and Southwestern motorways, each carrying three lanes of traffic up to 40m below the suburbs of Waterview and Owairaka. The tunnels will be the longest road tunnels in the New Zealand.

Doing the hard work is Alice, a 90m-long, 3100tonne tunnel borer. So far it has excavated 400,000m3 of spoil, and 12,070 concrete tunnel lining segments have been placed in her wake.

The 2574 NZ Transport Agency’s highways manager for Auckland and Northland, Brett Gliddon, says the southbound tunnel’s completion is a significant milestone in the project. The next five months will be taken up with turning Alice around so she can dig the northbound tunnel.

“While it is not unusual to turn a tunnel boring machine, what is extraordinary about this turn is the sheer size of the machine and constricted space in which the manoeuvre will take place,” says Mr Gliddon.

Well-Connected Alliance project manager John Burden says the break through, turnaround and restart of the tunnel borer are particularly challenging.

A large, steel restraining frame was installed to prevent the face of the tunnel from collapsing as Alice broke through. This will be removed and a concrete receiving cradle installed under the borer. Alice will then be disconnected into four parts – the cutting head and three trailing gantries – and each piece pushed from the completed tunnel, one at a time, onto a steel cradle, dragged sideways and turned 180° using large pulling jacks and lots of grease – 200litres of lanolin from New Zealand sheep, to be precise.

In December, Alice will be set up into launch position at the headwall and the first of her gantries reconnected along with a smaller and lighter temporary second gantry, as there will not be enough room for the other gantries. The main drive will begin in March next year. Once she has bored 300m of the second tunnel the temporary gantry will be removed and the second and third gantries will be reattached.

A fourth gantry, which operates independently of Alice to install a culvert on the floor of the tunnel that will carry services needed for its operation, will also need to be turned before it can resume work.

The Waterview Connection project also includes building surface connections to the existing motorways, 9km of new cycleway, and new community amenities such as playgrounds and walkways.

The tunnel is a key feature of five interconnected projects currently underway to the west of the city to complete the Western Ring Route, a 47km-long motorway alternative to State Highway 1 that runs through the heart of Auckland’s congested central city. These, along with a sixth, already-completed interchange upgrade project, have a total price tag of NZ$1.4 billion (US$1.09 billion).

Rubbing shoulders with the Waterview Connection is the 4.8km-long, Causeway Upgrade project. Although not as spectacular as the tunnel, this project is vital to the improvement of the motorway network. It sees more than 90,000 vehicles/day, along with many users of the cycleway alongside the motorway.

The causeway has been prone to flooding and debris during extremely high tides and adverse weather, and is subject to traffic congestion during peak hours. The upgrade will raise it by 1.5m for half its length and widen the existing dual three-lane motorway to five lanes westbound and four lanes city-bound, plus bus shoulder lanes and an improved cycleway.

In many ways this project is fairly straightforward, however, the road passes through a marine reserve so requires particular environmental consideration. The construction site is also a narrow corridor adjacent to high-speed motorists, increasing the safety risks for workers on site.

Another three adjacent projects, the Great North Road to St Lukes interchange, the Te Atatu Road interchange and the Lincoln Road interchange, are also underway.

As the projects are all linked but being undertaken by three different teams, one of the biggest challenges is ensuring excellent communication between the project teams.

“It’s an integrated programme with lots of traffic shifts. We’ve got quite a lot of people working on the detail,” says Causeway Alliance project manager Mark Evans. “We have management, operational and governance meetings frequently to ensure we know who can do what and when.

“A lot of planning has gone in to get this right.”

For more information on companies in this article

Related Content

  • Huge investment for Moscow’s motorway routes
    May 1, 2015
    Huge investments being made in building several outbound routes in Moscow and the Moscow region – Eugene Gerden writes. Up to US$20 billion (900 billion Roubles) will be invested in the building of several outbound routes in Moscow and the Moscow region during the next few years, according to an official spokesperson of the Russian Ministry of Transport. It is planned that the routes will be built as flyovers above the railroad tracks in the Yaroslavl, Kazan, Riga and Paveletskaya directions of the
  • Georgia’s on Sandvik’s mind
    February 18, 2013
    Three Sandvik DX800 top-hammer hydraulic drills are said to be playing a key role in developing the new US$92 million Norfolk Southern Intermodal Site within Charlotte Douglas International Airport in the US state of Georgia. The site, in the Georgia town of Austell, encompasses nearly 200 acres of ground, with a granite rock formation lying less than 100m away from a very active runway of the very busy airport. The ground will be turned into an ‘intermodal yard’, meaning that cargo carried there on Norfolk
  • Bid to solve pothole problem
    July 3, 2012
    The UK now has new guidance designed to ensure that when utilities companies dig up the road surface, they leave proper repairs once the work is complete. It is estimated that poorly replaced road surfaces mean there are around 90,000 remedial works each year, adding inconvenience to motorists and cyclists. Many of the road repairs are not properly carried out, increasing the risk of potholes forming and further defects. This significantly increases the risk of accidents and of damage to vehicles. The new l
  • BMO Entreprenør wins Vestland bridges deal
    March 22, 2024
    The work, in western Norway, includes concrete rehabilitation, steel surface-treatment, removal and installation of bridge railings and moisture insulation.