SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • ARTBA predicts growth in transport construction
    December 2, 2016
    Modest growth in transport construction is predicted in the US in 2017 by the American Road & Transportation Builders Association (ARTBA). According to a report by ARTBA chief economist, Dr Alison Premo Black, total transportation construction and related market activity is expected to grow 1.3% in 2017, driven largely by increases in highway and bridge private construction activity supporting residential and commercial developments. In 2017, the market is expected to reach US$247.8 billion, up from $244
  • Lithuania: EIB to issue loan for Vilnius-Utena A14 highway
    September 21, 2016
    The European Investment Bank (EIB) is looking at issuing a €40 million loan towards reconstruction of Lithuania's Vilnius-Utena A14 highway. According to a notice by the EIB earlier this year, the project includes reconstruction of 58km highway, the main traffic artery between the capital and north-eastern regions of Lithuania. The government intends to procure the project as a public-private partnership under a 13-year concession contract, including a 3-year construction period. The bank noted that t
  • Pre-stressed bridge decks use modular formwork system
    July 9, 2012
    Imaginative formwork, often using modular components, is helping to shape some challenging bridges worldwide. Patrick Smith reports Traffic volumes in and around Prague have swollen massively in recent years, pushing the existing road network to the limits of its capacity. To permanently ease congestion in the Czech capital's centre, a multi-lane orbital motorway is under construction as a high capacity bypass for central Prague and to link up all the motorways and other major highways radiating from the ci
  • Vietnam: work on Phuoc Khanh cable stayed bridge to begin in August
    June 22, 2015
    Work on Vietnam’s 3.1km Phuoc Khanh cable stayed bridge will start in August after a deal was signed with the government in June. The contract was signed by the Vietnam Expressway Corporation and a consortium made up of Japanese contractor Sumitomo Mitsui and local partner Civil Engineering Construction Corporation (Cienco 4). The bridge is part of the 57km Ben Luc-Long Thanh Expressway project running through Long An Province, Ho Chi Minh City and Dong Nai province in southern Vietnam. The highway will a