SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • China's massive bridge opens
    February 15, 2012
    The world's largest bridge over water is now open to traffic. Measuring over 42km long the bridge links China's eastern port city of Qingdao with Huangdao Island.
  • Riyadh’s transport infrastructure upgrade programme
    August 29, 2013
    IRF chairman and mayor of Riyadh, Eng Abdullah A Almogbel, discusses the city’s massive infrastructure investment and the pressing need for this development work Saudi Arabian capital Riyadh is fast growing with a pressing need for additional transport infrastructure resulting in a massive investment programme. The oil industry has fuelled Riyadh’s rapid expansion from being a medium sized town just 100 years ago, to its status as a major city today. With the explosion in vehicle use during the 20th ce
  • Montreal to expand bus rapid transit on Pie-IX Boulevard
    June 5, 2018
    The Canadian province of Quebec tendered this month for expansion of the Pie-IX Boulevard bus rapid transit system between the cities of Laval and Montreal. The provincial government will contribute US$304 million out of which around $23 million will be for 28 new buses, according to the Canadian Broadcasting Corporation. Construction of the 11km stretch could start by October with completion in 2022. Pie-IX Boulevard, named after Pius IX, a Catholic pope, is a major thoroughfare on the island of M
  • Learning from Russia's controversial road project
    February 9, 2012
    The International Road Federation (IRF), founded in 1948, is the only world forum advocating better and safer roads through better road design and construction bearing in mind the user. It is a unique institution that brings together members active in road infrastructure from both the private and public sectors. The IRF promotes roads that are safe, economically viable and ecologically friendly. The IRF believes that a sound road infrastructure brings prosperity, fights poverty, furthers education and gi