SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • Europe-Asia road link
    February 9, 2017
    The governments of China, Kazakhstan, Belarus and Russia have finally approved a project for the building of a new transcontinental road, which will connect Asia and Europe. The new route is much-needed and will speed the transportation of cargo between the two continents, according to Maxim Sokolov, Russia’s Minister of Transport. The idea for the building of the road was first proposed by the European Commission around 2005. It was prompted by the ever growing volume of trade between the EU and Chin
  • German bridge demolition work assisted by Liebherr
    May 9, 2022
    Construction equipment from Liebherr has played an important role in the project to demolish a bridge in Germany.
  • Funding issue for Bangladesh tunnel but highway moving forward
    November 14, 2017
    Two major infrastructure projects in Bangladesh are experiencing rather different fates at present. A lack of suitable funding has resulted in the US$705 million Karnaphuli river tunnel project coming to a grinding halt. However the $1.53 billion contract for the Dhaka to Ashulia highway has now been awarded to the Chinese firm, China National Machinery Import and Export Corp (CMC). Chinese funding is intended to pay for the Karnaphuli Tunnel, but has so far been delayed and the Chinese contractor awarded
  • British Columbia awards Quartz Bridge deal
    March 22, 2021
    The Canadian province calls time on the old Quartz Creek Bridge.