SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • Weigh-in-motion for Bangabandhu Bridge
    July 8, 2022
    The bridge, in Bangladesh, will also have automatic number plate recognition cameras to identify overweight vehicles.
  • Aggregate Industries lightens the load for the Acton Swing Bridge
    October 2, 2018
    Aggregates Industries recently lightened the load for the 73m-long bow string truss Acton Swing Bridge in England. When opened in 1933, it was the first floating swing bridge in the UK – floating on a pontoon. The 84-year-old bridge, which is cared for by the Canal & River Trust charity, carries the busy A49 road over the River Weaver Navigation, in the county of Cheshire. A recent €1.7 million complete refurbishment included strengthening works to the underside of the bridge as well as improvements to its
  • Construction consortium captures key contract in Australia
    April 29, 2015
    The Pacific Complete consortium is the preferred Delivery Partner for the NSW Government’s Woolgoolga to Ballina Pacific Highway upgrade in Australia. The Pacific Complete consortium comprises Laing O’Rourke and Parsons Brinckerhoff. The A$4.3 billion highway upgrade is Australia’s largest regional infrastructure project. NSW Roads and Maritime Services will deliver the project using a Delivery Partner model similar to the approach used for the highly successful construction project for the London Olympic
  • BAM, PGGM and Habau win German A10-A24 contract
    December 20, 2017
    A consortium of BAM-PGGM and HABAU has been appointed preferred bidder for extension of Germany’s A10-A24 motorway from Neuruppin to Pankow, near Brandenburg. The public-private partnership deal covering nearly 65km is worth around €1 billion over the 30 years of the contract, according to infrastructure project management company DEGES.