Mersey Gateway Project reaches half-way point across the Mersey

The Mersey Gateway project in England has passed a significant milestone, with over half of the main bridge deck stretching across the River Mersey. Work to install stay cables on the main bridge also passed a key point, with installation of the 31st 150m long cable – the halfway point for stay cable installations on the pylon. When complete, 146 stay cables will support the 1km-long reinforced concrete bridge, with a combined load-bearing weight of more than 53,000tonnes. “We’re now more than 50
March 10, 2017 Read time: 2 mins
The 6126 Mersey Gateway project in England has passed a significant milestone, with over half of the main bridge deck stretching across the River Mersey.

Work to install stay cables on the main bridge also passed a key point, with installation of the 31st 150m long cable – the halfway point for stay cable installations on the pylon.
 
When complete, 146 stay cables will support the 1km-long reinforced concrete bridge, with a combined load-bearing weight of more than 53,000tonnes.
 
“We’re now more than 50% through this highly visual phase of the Mersey Gateway construction,” said Gareth Stuart, project director of the Merseylink construction joint venture. “People will be able to see the stay cables connected to the bridge deck as it emerges across the river week by week.”
 
Each stay cable consists of up to 91 steel strands that sit inside a stay pipe – the outer casing that provides protection from weathering. More than 1,300km of the strands will be used on the project.

Every single strand needs to be installed individually, explained Merseylink’s design manager, George Moir. “It’s gone well so far, and we’re installing around six stays per week from the three pylons. The first two strands are threaded through the stay pipe then the tower crane lifts the pipe up to the anchor point in the upper pylon where the top ends of the strands are fixed into place.
 
“The bottom ends of the strands are then attached to the anchor point in the bridge deck and stressed using a hydraulic system. This enables us to get the correct level of tension needed to support that segment of bridge deck,” said Moir. “We then use a winch system through the stay pipe to winch the remaining strands up one by one. Once all of the strands have been installed they sit in parallel inside the stay pipe to form the stay cable.”
 
The stay cables vary in length; with the shortest measuring approximately 41m and the longest measuring 226m.

For more information on companies in this article

Related Content

  • The radically changing face of UK highways management
    May 14, 2014
    The British Government policy paper ‘Action for Roads: A network for the 21st century’ sets out radical change to the strategic way roads are funded and managed – including plans to turn the Highways Agency into a Government-owned company and a pledge to invest over €33.4 billion (£28 billion) in roads maintenance between 2015 and 2020. Jenny Moten, Highways Agency divisional director for Network Services, gave a keynote presentation on the new approach to strategic highways management during the Road Safet
  • Machine Control sector is the place for acquisitions
    January 22, 2014
    The machine control sector has been lively in recent months with a major acquisition, the unveiling of new software innovation and landmark testing of new technology to monitor paving temperature. Guy Woodford reports The state road construction authority in the German state of Saxony-Anhalt (LSBB Saxony-Anhalt) has become the first nationally to test MOBA’s new PAVE-IR Scan temperature measurement system at a works site.
  • An array of crushing and screening innovations was presented at the recent INTERMAT 2012 exhibition
    July 19, 2012
    The crushing and screening phase is a crucial component in aggregate production and new development will help optimise performance - Mike Woof reports Crushing and screening is a key part of the quarrying cycle and has a huge impact on overall operating performance. Optimising operations will cut running costs, reduce materials wastage and also provide a more consistent product quality, boosting cost-effectiveness dramatically. An array of innovations were revealed to the market at the recent INTERMAT 2012
  • Landmark bridge for Italy?
    August 9, 2023
    The news that the Italian Government is once again considering building a bridge spanning the Messina Strait is of major significance for the construction sector, as well as for the country.