Mersey Gateway Project reaches half-way point across the Mersey

The Mersey Gateway project in England has passed a significant milestone, with over half of the main bridge deck stretching across the River Mersey. Work to install stay cables on the main bridge also passed a key point, with installation of the 31st 150m long cable – the halfway point for stay cable installations on the pylon. When complete, 146 stay cables will support the 1km-long reinforced concrete bridge, with a combined load-bearing weight of more than 53,000tonnes. “We’re now more than 50
March 10, 2017 Read time: 2 mins
The 6126 Mersey Gateway project in England has passed a significant milestone, with over half of the main bridge deck stretching across the River Mersey.

Work to install stay cables on the main bridge also passed a key point, with installation of the 31st 150m long cable – the halfway point for stay cable installations on the pylon.
 
When complete, 146 stay cables will support the 1km-long reinforced concrete bridge, with a combined load-bearing weight of more than 53,000tonnes.
 
“We’re now more than 50% through this highly visual phase of the Mersey Gateway construction,” said Gareth Stuart, project director of the Merseylink construction joint venture. “People will be able to see the stay cables connected to the bridge deck as it emerges across the river week by week.”
 
Each stay cable consists of up to 91 steel strands that sit inside a stay pipe – the outer casing that provides protection from weathering. More than 1,300km of the strands will be used on the project.

Every single strand needs to be installed individually, explained Merseylink’s design manager, George Moir. “It’s gone well so far, and we’re installing around six stays per week from the three pylons. The first two strands are threaded through the stay pipe then the tower crane lifts the pipe up to the anchor point in the upper pylon where the top ends of the strands are fixed into place.
 
“The bottom ends of the strands are then attached to the anchor point in the bridge deck and stressed using a hydraulic system. This enables us to get the correct level of tension needed to support that segment of bridge deck,” said Moir. “We then use a winch system through the stay pipe to winch the remaining strands up one by one. Once all of the strands have been installed they sit in parallel inside the stay pipe to form the stay cable.”
 
The stay cables vary in length; with the shortest measuring approximately 41m and the longest measuring 226m.

For more information on companies in this article

Related Content

  • HDR’s twin Rockingham bridges win PCI award
    February 12, 2021
    The award from the Precast Concrete Institute is a third win for HDR projects.
  • Recycled materials
    May 30, 2023
    A road building firm in China is benefiting from the use of a new asphalt plant able to handle a high percentage of recycled asphalt pavement (RAP) in the mix. The firm is operating a Lintec CSM4000HRC asphalt mixing plant that is equipped with a hot recycling system.The plant is being operated by Lu An Highway Industry in China’s Anhui province, providing high-quality asphalt for the S244 regional expressway and other expressway and road maintenance projects.
  • Greener transport infrastructure
    February 16, 2024
    Crossing the carbon challenge: Pioneering carbon reduction on the UK’s ‘greenest’ major infrastructure project Paul Taylor – AtkinsRéalis Carbon Manager, Lower Thames Crossing Roads North
  • Yunex Traffic management for Hamburg
    April 28, 2022
    More than 150,000 vehicles pass along the A7 in Hamburg, Germany, every day – increasing regularly. To ensure continued safety on the route, highway operator Die Autobahn launched an extensive renovation project on the A7. Traffic technology on the city highway will be optimised, digitised and connected in 18 construction phases.