Mersey Gateway Project reaches half-way point across the Mersey

The Mersey Gateway project in England has passed a significant milestone, with over half of the main bridge deck stretching across the River Mersey. Work to install stay cables on the main bridge also passed a key point, with installation of the 31st 150m long cable – the halfway point for stay cable installations on the pylon. When complete, 146 stay cables will support the 1km-long reinforced concrete bridge, with a combined load-bearing weight of more than 53,000tonnes. “We’re now more than 50
March 10, 2017 Read time: 2 mins
The 6126 Mersey Gateway project in England has passed a significant milestone, with over half of the main bridge deck stretching across the River Mersey.

Work to install stay cables on the main bridge also passed a key point, with installation of the 31st 150m long cable – the halfway point for stay cable installations on the pylon.
 
When complete, 146 stay cables will support the 1km-long reinforced concrete bridge, with a combined load-bearing weight of more than 53,000tonnes.
 
“We’re now more than 50% through this highly visual phase of the Mersey Gateway construction,” said Gareth Stuart, project director of the Merseylink construction joint venture. “People will be able to see the stay cables connected to the bridge deck as it emerges across the river week by week.”
 
Each stay cable consists of up to 91 steel strands that sit inside a stay pipe – the outer casing that provides protection from weathering. More than 1,300km of the strands will be used on the project.

Every single strand needs to be installed individually, explained Merseylink’s design manager, George Moir. “It’s gone well so far, and we’re installing around six stays per week from the three pylons. The first two strands are threaded through the stay pipe then the tower crane lifts the pipe up to the anchor point in the upper pylon where the top ends of the strands are fixed into place.
 
“The bottom ends of the strands are then attached to the anchor point in the bridge deck and stressed using a hydraulic system. This enables us to get the correct level of tension needed to support that segment of bridge deck,” said Moir. “We then use a winch system through the stay pipe to winch the remaining strands up one by one. Once all of the strands have been installed they sit in parallel inside the stay pipe to form the stay cable.”
 
The stay cables vary in length; with the shortest measuring approximately 41m and the longest measuring 226m.

For more information on companies in this article

Related Content

  • Somague consortium wins deal for Ponte 25 de Abril
    September 27, 2018
    Portuguese infrastructure operator Infraestruturas de Portugal has awarded Somague a €12.6 million maintenance and refurbishment contract for work on the bridge Ponte 25 de Abril. Somague is heading up a consortium that includes Sociedade de Montagens Metalomecânicas and Reparação, Consolidação e Modificação de Estruturas. The 25 de Abril, a 2.3km suspension bridge for vehicles and trains over the Tagus River, connects Portugal’s capital city Lisbon to the municipality of Almada. It was built by the A
  • FlexiPole installed on famous Clifton Bridge
    April 11, 2013
    A number of Ritherdon passively-safe electroluminescent (EL) FlexiPole signpost systems have now been installed on the historic Clifton Suspension Bridge in Bristol, west England. Completed in 1864, the Bridge was originally designed to provide a safe crossing across a gorge for horse-drawn traffic; the chosen method of transport in the 19th century. However it now accommodates 21st century commuter traffic with in excess of 11,000 vehicles crossing the Bridge every day. The custodians of Clifton Suspension
  • Key Botswana road network gets an upgrade
    June 30, 2014
    Representing an investment of around US$113 million, Botswana’s A1 national road between Tonota and Francistown is undergoing a major upgrade This single-lane section is being progressively transformed into a north- and southbound dual carriageway, crossing four existing river bridges along the way. A strategically important transportation route for both Botswana and the southern African region, the A1 passes through Francistown, the nation’s second largest city, heading northwards to end at the Zimbabwe b
  • New heavy lift crawler crane from Sany
    January 6, 2017
    Sany America is offering a new 500 tonne class crawler crane aimed to fill a gap in its range that suits duties in infrastructure projects. The Sany SCC8500 is well-suited for construction of 100m wind towers and placing 2.5MW nacelles. The SCC8500 can make these lifts with a straight boom and an offset wind tip, with no need for a back mast. With a full complement of attachments and options, including fixed jib, luffing jib and the SANY UltraLift package, the SCC8500 can also be used in infrastructure proj