Work is well in hand on the Mersey Gateway Bridge project in the UK. The bridge construction work has now reached a major milestone. The south pylon of the Mersey Gateway has been completed, marking the project’s highest point in the River Mersey estuary. The south pylon stands 125m high, with the north pylon due to be completed in the next few days. The smaller central pylon, which is due to be finished in November, will be 80m high. A specialist automatic climbing system is being used to construct the
October 6, 2016 Read time: 2 mins
The Mersey Gateway Bridge project in the UK has reached a major milestone in its construction
Work is well in hand on the 6126 Mersey Gateway Bridge project in the UK. The bridge construction work has now reached a major milestone. The south pylon of the Mersey Gateway has been completed, marking the project’s highest point in the River Mersey estuary. The south pylon stands 125m high, with the north pylon due to be completed in the next few days. The smaller central pylon, which is due to be finished in November, will be 80m high.

A specialist automatic climbing system is being used to construct the bridge pylons. This equipment builds one vertical 5m section at a time. It then repeatedly climbs upwards to create the next section until the structure is complete. Construction teams have completed 30 sections for the south pylon and 27 for the north pylon. In all, 21 sections will be built for the central pylon. A total of 2,230m3 of concrete was poured for the south pylon, and 1,890m3 for the north pylon.

Gareth Stuart, project director at Merseylink, said, “Hitting the highest point on the project is a significant milestone and it’s a testament to the tenacity and expertise of our construction crews who have worked extremely hard, often in challenging conditions, to get the job done. We’ll be holding a special site celebration to thank all of the teams involved.”

The next phase of work involves installing steel stay cables to connect the three bridge pylons to the main bridge deck. This will begin in the next couple of weeks. Halton’s six-lane river crossing is on schedule to open in autumn 2017.

For more information on companies in this article

Related Content

  • Bihar crossing for Ganges River
    November 16, 2016
    A loan facility from the Asian Development Bank (ADB) will help fund work on the project to construct a new bridge over the River Ganges in India’s Bihar State. Because of the width of the river at this point, the bridge will be close to 10km in length, making it the longest in India. The new bridge will improve transport connections between the north and south of the state and the project is expected to cost around US$500 million. Building the bridge will help develop transport and trade in the area, as we
  • Peri has Polish bridge covered
    February 6, 2012
    A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used. Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.
  • Concrete paving a smoother surface using machine control technology
    May 17, 2017
    Innovative technology has been used to deliver a smooth concrete road surface on a busy stretch of highway in Nebraska. Much-needed work on a busy section of Interstate 80 has been carried out in Nebraska to improve the road surface. This is one of the most important highways in the US, providing a link that stretches right across the country between the east and west coasts. This busy highway carries a high percentage of heavy truck traffic as it is a vital transport route. However this constant flow of la
  • Better roads through asphalt plant innovation
    August 19, 2014
    In Africa, one of the world’s fastest-growing cities is using the latest asphalt plant technology to boost its road maintenance work; while leading firms are finding their innovative solutions in demand in Europe and the Americas. Guy Woodford reports A new up to 180tonnes/hour Marini UltiMAP 2000 plant is helping Lagos State Public Works in Lagos, Nigeria implement a five-year strategic road map aiming to ensure high standards of road maintenance and improve infrastructural development across the city of m