Mersey Gateway Bridge project progress

Work is well in hand on the Mersey Gateway Bridge project in the UK. The bridge construction work has now reached a major milestone. The south pylon of the Mersey Gateway has been completed, marking the project’s highest point in the River Mersey estuary. The south pylon stands 125m high, with the north pylon due to be completed in the next few days. The smaller central pylon, which is due to be finished in November, will be 80m high. A specialist automatic climbing system is being used to construct the
October 6, 2016 Read time: 2 mins
The Mersey Gateway Bridge project in the UK has reached a major milestone in its construction
Work is well in hand on the 6126 Mersey Gateway Bridge project in the UK. The bridge construction work has now reached a major milestone. The south pylon of the Mersey Gateway has been completed, marking the project’s highest point in the River Mersey estuary. The south pylon stands 125m high, with the north pylon due to be completed in the next few days. The smaller central pylon, which is due to be finished in November, will be 80m high.

A specialist automatic climbing system is being used to construct the bridge pylons. This equipment builds one vertical 5m section at a time. It then repeatedly climbs upwards to create the next section until the structure is complete. Construction teams have completed 30 sections for the south pylon and 27 for the north pylon. In all, 21 sections will be built for the central pylon. A total of 2,230m3 of concrete was poured for the south pylon, and 1,890m3 for the north pylon.

Gareth Stuart, project director at Merseylink, said, “Hitting the highest point on the project is a significant milestone and it’s a testament to the tenacity and expertise of our construction crews who have worked extremely hard, often in challenging conditions, to get the job done. We’ll be holding a special site celebration to thank all of the teams involved.”

The next phase of work involves installing steel stay cables to connect the three bridge pylons to the main bridge deck. This will begin in the next couple of weeks. Halton’s six-lane river crossing is on schedule to open in autumn 2017.

For more information on companies in this article

Related Content

  • Cheaper, greener and less smelly; it’s all about the additives
    August 20, 2015
    The demand for bitumen additives is set to increase. Kristina Smith reports on some of the companies who are preparing to meet that increased demand. The variation in quality and composition of bitumen around the world is something that has been well-documented in these pages. Processing technologies for crude oil are changing, the way bitumen is traded is changing, and the final result can be a product that may not be all it seems – or huge variations from one shipment to another. Help is at hand, however,
  • Grand achievement for Intermountain
    July 18, 2012
    A versatile solution has helped with a tricky project at the Grand Canyon in the US – Pierre Peltier When Intermountain Slurry Seal, a division of Granite Construction, submitted its bid in 2009 to repair roads and parking lots along the Grand Canyon’s North Rim, the company knew the job would come with challenges. The remote roads leading from Jacob’s Lake, Arizona, to the North Rim Lodge had deteriorated to a point that the Federal Highway Association’s (FHWA) Central Federal Lands (CFL) Highway Division
  • Kazakhstan bridge project complete
    December 16, 2016
    The opening of a new bridge in Kazakhstan that spans the Irtysh River is now offering a shorter route for drivers. The link is 12.3km long and is now the longest such structure in Central Asia, while the project cost around US$157 million. Its length was necessary as the bridge crosses a floodplain area, with a channel that can widen considerably following periods of heavy rain. Located in the country’s Pavlodar region, the bridge cuts the route used previously by over 40km. The bridge is expected to carry
  • Tunnel breakthrough for new Auckland link in New Zealand
    October 8, 2014
    Auckland’s Western Ring Route project update - Mary Bell writes. A number of integrated projects in Auckland, New Zealand, will improve the lot of road users and cyclists, and significantly alter the topography of the city’s motorway. On September 29th the tunnel boring machine digging the first of twin road tunnels beneath the city broke into daylight after 10 months underground. The new 2.4km-long Waterview tunnels will connect the city’s Northwestern and Southwestern motorways, each carrying three lane