Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • Road transport must evolve in line with users’ needs
    April 12, 2012
    At its annual plenary meeting held on 25 May 2010, during the 16th IRF World Meeting in Lisbon, the European Road Federation (ERF) elected a new President in the person of Jacobo Díaz Pineda. Mr. Díaz Pineda has been the Director General of the Spanish Road Association (AEC) since September 2006, and is also President of the Ibero-American Road Institute (IVIA). We took advantage of his presence in Lisbon to ask him a few questions about his new responsibilities:
  • Colombian road construction project well underway
    April 14, 2023
    Work is well underway for a key Colombian road construction project.
  • Ma(r)king the roads readable for self-driving cars
    December 20, 2021
    CAV, V2X, C-ITS, CCAM – the acronyms are differing, but they all have in common that they denominate the linking of road infrastructure and vehicles with the aim to improve traffic flow, reduce emissions and make traffic safer and our journeys more convenient.
  • New tunnel for Colombian capital
    February 3, 2014
    Pre -feasibility studies are commencing for a new tunnel project in Colombia capital Bogota. The tunnel is set to link Bogota’s north side with La Calera and the studies should be completed by April 2014. The project is expected to cost in the region of US$198.76 million to construct and will be for a 4.5km tolled tunnel. The project will be challenging however and will take up to four years to complete. The route will run from Street 170 in northern Bogota, linking the Perimetral Oriental ring road that is