Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • Stonehenge Bypass Tunnel project facing judicial review
    February 19, 2021
    The UK’s Stonehenge Bypass Tunnel project is now facing a judicial review.
  • US$2 billion Pakistan highway project
    September 10, 2024
    A US$2 billion Pakistan highway project is getting the go ahead.
  • Nepal's road connectivity is pushing ahead
    December 17, 2012
    A new project by the Government of Nepal recently connected Mugu a distant, mountainous and remote district of Karnali Zone to the country’s road connectivity and has been the 73rd district of the 75 in road connection. The road was opened officially by Nepal’s prime minister, Dr Baburam Bhattarai, while The minister for Physical Planning and Transport Management Hrideyesh Tripathy, finance minister Barha Man Pun, chief of army staff Gaurav Shumser Rana and vice-chairman Dipendra Bahadur Chhetri of Nationa
  • Golden opportunities in the MINT - Mexico, Indonesia, Nigeria, Turkey
    May 21, 2015
    Mexico, Indonesia, Nigeria, Turkey – Global Report offers up some food for thought about where smart money might be headed within the next several years – David Arminas writes China’s rate of growth may be slowing down, but other South East Asian companies are being quick to offer alternate investment opportunities, notably Indonesia. Nigeria, too, has had issues with security of investment. But there are signs that the government may be getting serious at last about tightening up rules and regulation