Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • Driving safely to cut risks for road users
    August 24, 2015
    Regulations in France covering driving have become tougher. In a bid to tackle distracted driving, French drivers are now banned from using hands-free phone kits that use headsets while at the wheel. This follows research showing that the use of hands-free kits is only slightly less dangerous than holding a phone in the hand while at the wheel. French drivers are also forbidden to eat, apply make-up, read a map or listen to very loud music when behind the wheel. Meanwhile headphones or wireless earpieces ar
  • Road safety is an EU priority
    March 2, 2012
    The preparation of the new EU Road Safety Policy for the next decade will take place during Spain's presidency of the EU. Patrick Smith reports. An the past 10 years, half a million people have been killed on European Union roads, with road crashes costing an annual €160 billion or 2% the EU's GDP.
  • Bilbao benefits from major tunnel project
    February 10, 2012
    The northern Spanish city of Bilbao looks set to benefit from a major tunnel construction project aimed at reducing traffic congestion on its vehicle clogged streets. The city is building a new underground metro section, Line 3, which will help carry commuters to and from the city's commercial centre and help reduce vehicle journey times on the surface. This project is also making use of the latest piece of tunnelling equipment from Sandvik, the MT520 roadheader, a powerful machine designed and built at
  • Algeria tunnel project restarting
    April 15, 2015
    In Algeria the Japanese contracting consortium Cojaal is taking over work on the Djebel Ouahch tunnel project. This move represents a return to the positive for Cojaal in Algeria as the consortium previously had its contract on the East-West highway project terminated. Carrying on construction at Constantine, consortium Cojaal will take over work on the Djebel Ouahch tunnel. The project has faced recent challenges as the tunnel collapsed on the 1st of January 2014. In addition to the tunnel, the complete pr