First deck span completed for Mersey Gateway's north approach viaduct

The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.
February 12, 2016 Read time: 2 mins

The 6126 Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed.

The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.

The MSS, which acts as a giant concrete mould, was specially designed for the Mersey Gateway Project. It is being used to build the two elevated approach viaducts over the Mersey estuary.

The span connects the beginning of the approach viaduct from the north abutment in Widnes to the first supporting pier. It measures around 60m long and 18m wide and is angled at 5 degrees to allow vehicles to travel safely around the curve of the approach road.

Construction teams worked around the clock to get the span ready. This involved pouring 1,146m3 of concrete into the MSS non-stop over 34 hours.


"This is a real achievement for the project and a milestone that we've been looking forward to with anticipation,” said Declan Cannar, Merseylink's general foreman in charge of the MSS operation. “We're now busy preparing the MSS so it's ready to cast the next section."

The approach viaduct deck is being constructed in three phases. The deck spans are constructed first by the MSS, then a deck slab is built on top of the span, and finally the outer deck or ‘wings' are built by a wing traveller machine to provide the full six lane width of the approach road.

The MSS has moved to its second casting position ready for work to begin on the next span, which will be cast in March.

View Trinity in action by clicking here.
%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal www.merseygateway.co.uk/live-view Visit www.merseygateway.co.uk/live-view false http://www.merseygateway.co.uk/live-view false false%>

For more information on companies in this article

Related Content

  • Pilosio exhibits its durable P300 formwork at bauma
    January 6, 2017
    Among Pilosio’s comprehensive range of formwork solutions on show at bauma will be the Italian firm’s P300 formwork. Used during the recent construction of a 560m overpass in Bucharest, Romania the P300 is said to be based on a 100x300cm base panel with a few simple accessories, such as a quick connection block to allow extremely rapid framework operations, and a varnished frame and surface counter-cast in 18mm thick, high resistance, multi-layered Finnish panels to ensure high number of uses.
  • Pilosio exhibits its durable P300 formwork at bauma
    February 15, 2013
    Among Pilosio’s comprehensive range of formwork solutions on show at bauma will be the Italian firm’s P300 formwork. Used during the recent construction of a 560m overpass in Bucharest, Romania the P300 is said to be based on a 100x300cm base panel with a few simple accessories, such as a quick connection block to allow extremely rapid framework operations, and a varnished frame and surface counter-cast in 18mm thick, high resistance, multi-layered Finnish panels to ensure high number of uses.
  • Guntert & Zimmerman is offering sophisticated stringless paving controls
    January 6, 2017
    The NoLine system now offered by Guntert & Zimmerman for its concrete slipform pavers offers the capability to do away with stringlines for controlling paving oeprations. This kit is offered as an option on all G&Z pavers and support equipment and comprises a software upgrade and a hardware kit. The NoLine software upgrade integrates the stringless technology directly into the paver’s CANBus network. Meanwhile the NoLine hardware kit provides telescopic masts for the total station prisms for use on the pave
  • Link-Belt unveils the next generation of its RTC-80110 Series II large rough terrain crane series
    January 6, 2017
    merican crane builder Link-Belt will be showing off the latest in its line of mid-range rough terrain cranes at Bauma, the RTC-8080 Series II, which offers a fully-powered, four-section, 38.7 m (127 ft) long main boom. The RTC-8080 Series II has a two-mode telescope proportioning system known as A-max and three on-board fly options allow operators to use at least four manual offset positions fixed at 2, 15, 30, and 45 degrees. One of the three on-board fly offerings is a 3-piece, bi-fold lattice fly, which