Delays have hit Chile’s Chacao Bridge project

Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
August 28, 2013 Read time: 2 mins
Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with Chiloé Island over the Chacao Channel. According to Chile's public works ministry, MOP, has moved back the tender process for the project towards the end of 2013.

The concession should be awarded in early 2014 with construction work itself commencing in 2015 and the structure opening to traffic in 2019. Eight consortia pre-qualified for the tender process. These are: Isei Joint Venture, Constructora Puente Chacao (CPC), 3959 Sacyr Samsung 3220 Parsons Puente Chacao, Consorcio Puelche, China Railwaygroup Limited, 3366 China Road and Bridge Corporation, Consorcio Cai Cai Vilu and Consorcio 1511 OAS-236 Hyundai-5549 Systra-Aas Jakobsenv.

Work on the bridge was original supposed to start in 2007 with its opening planned for 2012. However, a substantial increase in the costs estimated by the project team of designer and contractor showed that the price would exceed the limit imposed by the 968 Chilean Government. The project was cancelled, prompting an outcry from those on the island and was then revived in 2009 as a fall in the cost of steel made it economically feasible once more.

For more information on companies in this article

Related Content

  • Towers of power: California’s Gerald Desmond Bridge Replacement
    May 8, 2019
    Challenging ground conditions meant a design rethink - and some engineering firsts - for California’s Gerald Desmond Bridge Replacement Project* The Port of Long Beach on Terminal Island south of Los Angeles is the second-busiest container port in the US. It handles around 15% of all imported goods, much of it with Asia. As the Port of Long Beach was growing in importance over the past half century, the 51-year-old Gerald Desmond Bridge has faithfully been delivering thousands of daily commuters to wo
  • Paraguay’s plan for road rebuilding
    September 30, 2015
    Paraguay’s Ministry of Public Works and Communications (MOPC) will award a series of road projects worth around US$1.3 billion in early 2016. These project include work on the first section of the bi-oceanic corridor, the reconstruction of Route 9, the expansion of Routes 2 and 7 and the second bridge connecting Paraguay with Brazil. The tender process for Route 9 from Remanso Bridge to the city of Mariscal Estigarribia will open shortly and the project is expected to cost around $380 million. The tender fo
  • Hyundai E&C is working on Turkey’s new third Bosporus Bridge
    July 10, 2013
    Hyundai Engineering & Construction (Hyundai E&C) is to head a consortium building the lateral towers, aprons and suspension cables for the new Bosporus crossing in Turkey. Hyundai E&C will work in a consortium with its partner SK Engineering & Construction on the US$697 million project to construct the 2.16km Third Bosporus Bridge. This suspension bridge will feature eight lanes for motor vehicle traffic as well as two rail lines. With a width of 59m it will be the widest bridge in the world that carries a
  • Plans in hand for Colombian highway project
    December 5, 2013
    The Colombian authorities have plans in hand for a US$240 million highway upgrade project. In all, 10 groups have been pre-selected for the tender process for the work, according to a report by Business News Americas. The project is for upgrades and improvements to a 173km stretch of the Puerta de Hierro-Cruz del Viso highway. This work includes improvements to access roads in the area, which lies in Colombia’s northern Sucre, Bolívar and Atlántico departments. The country’s infrastructure agency, ANI, has