Delays have hit Chile’s Chacao Bridge project

Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
August 28, 2013 Read time: 2 mins
Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with Chiloé Island over the Chacao Channel. According to Chile's public works ministry, MOP, has moved back the tender process for the project towards the end of 2013.

The concession should be awarded in early 2014 with construction work itself commencing in 2015 and the structure opening to traffic in 2019. Eight consortia pre-qualified for the tender process. These are: Isei Joint Venture, Constructora Puente Chacao (CPC), 3959 Sacyr Samsung 3220 Parsons Puente Chacao, Consorcio Puelche, China Railwaygroup Limited, 3366 China Road and Bridge Corporation, Consorcio Cai Cai Vilu and Consorcio 1511 OAS-236 Hyundai-5549 Systra-Aas Jakobsenv.

Work on the bridge was original supposed to start in 2007 with its opening planned for 2012. However, a substantial increase in the costs estimated by the project team of designer and contractor showed that the price would exceed the limit imposed by the 968 Chilean Government. The project was cancelled, prompting an outcry from those on the island and was then revived in 2009 as a fall in the cost of steel made it economically feasible once more.

For more information on companies in this article

Related Content

  • Italy’s Messina Strait bridge design approved
    February 21, 2024
    The design has been approved for Italy’s Messina Strait bridge mega project.
  • Mozambique’ new bridge opens to traffic
    November 14, 2018
    Mozambique’s new suspension bridge connecting Maputo with Catembe is now open to traffic. The suspension bridge is the longest of its type in Africa, measuring almost 3km-long and surpassing the previous holder of this accolade, the Mapati Bridge in the Democratic Republic of Congo. The new bridge spans Maputo Bay and forms part of a new highway connection running from Mozambique’s capital, Maputo, all the way to the border with South Africa. The route will be of major benefit for Mozambique, helping to boo
  • Chile approves construction of the Agua Negra project through the Andes
    August 13, 2015
    Plans for a cross-continent upgraded road were recently boosted when Chile’s senate approved construction of its share of a major US$1.6 billion tunnel in the Andes Mountains. The Chilean approval comes after the Argentinian government gave the nod in March for construction on its section of the Agua Negra project. A tender for specific design work could be put out by September, according to the Argentinian newspaper Diario de Cuyo. The approvals resolve a number of bilateral issues including taxation
  • Messina Strait bridge tender due?
    August 10, 2023
    The Messina Strait bridge tender is due to open soon.