Cost increases for major Chilean highway project

The cost of Chile’s Vespucio Oriente highway project is increasing, while its completion also looks set to be delayed. A 13% budget increase is now required due to additional costs from a number of factors such as urban landscaping, according to Business News Americas. The Américo Vespucio Oriente (AVO) expressway is being built in Chilean capital Santiago and was originally expected to cost in the region of US$940 million. However Chile’s Public Works Ministry, MOP, has said that the route will now cost so
November 15, 2013 Read time: 3 mins
The cost of Chile’s Vespucio Oriente highway project is increasing, while its completion also looks set to be delayed. A 13% budget increase is now required due to additional costs from a number of factors such as urban landscaping, according to Business News Americas. The Américo Vespucio Oriente (AVO) expressway is being built in Chilean capital Santiago and was originally expected to cost in the region of US$940 million. However Chile’s Public Works Ministry, MOP, has said that the route will now cost some $1.06 billion. The project is for a 40-year concession package that includes building and operating a 9.3km underground expressway through Santiago. The route runs from El Salto Avenue to Príncipe de Gales Avenue, under the existing Américo Vespucio beltway. Because of the route, the project will be both complex and challenging and MOP also said that firms or joint ventures interested in participating in the tender will now have until December 30th 2013 to submit technical bids, compared to the previous deadline of November 22nd 2013. The ministry will then announce the economic proposals for the concession on January 20th 2014.

The new AVO route will be built on two levels, each one carrying a one-way, three-lane expressway. Road capacity will increase to 8,000 vehicles/hour. The project is required as Santiago suffers chronic congestion, particularly at peak periods. The authorities split the long-delayed AVO tender in two, given the complexity of the project, which will run through five municipalities in eastern Santiago. The new AVO route will provide the missing link in the city's beltway and was originally intended to run underground for 13km, joining El Salto with Grecia Avenue. However, this plan attracted strong protests from residents of the La Reina and Peñalolén districts. The 968 Chilean Government opted to split the project and call a tender only for the first 9.3km stretch. However in March 2014 Chile will have a new election and responsibility for the project will then be passed to whichever party wins. Opposition candidate for the presidency, Michelle Bachelet, has previously said she opposed the splitting of the tender and this could further add to the wrangling over the project, as well as adding additional delays.

For more information on companies in this article

Related Content

  • Colorado river bridge relieves congestion
    February 7, 2012
    Built in the shadow of the Hoover Dam, a new bridge is set to takes its place as another major tourist attraction. Patrick Smith reports
  • Budapest’s Széchenyi Chain Bridge reopens
    December 22, 2022
    Although open, for the time being only buses, taxis, bicycles and motorcycles can use the famous 19th century bridge that links Buda and Pest which make up the Hungarian capital.
  • Bullish bauma China 2014 boomed with record results
    December 1, 2014
    The bauma China 2014 event held in Shanghai from 25th-28th November set a series of records, most notably with its attendance hitting 191,000 visitors, an increase of 6% from the previous show in 2012. The show had a very strong international presence with visitors from 149 countries, as well as a strong showing in respect to international buyers, up some 12% from 2012. Meanwhile there were 3,104 exhibitors from 41 countries, an increase of 14%. The four day bauma China 2014 event was held at the Shanghai N
  • The most dangerous times on US roads
    July 2, 2018
    Newly available data from the Insurance Institute for Highway Studies (IIHS) shows the most dangerous days for drivers on US roads. The research studied fatal crashes that occurred between 1998 and 2014, revealing that summer and early Autumn have the highest rates of fatal road crashes. The risk of crashing is higher at the weekend than during the working week, with the 3pm to 7pm time slot having a particularly high risk of road fatalities. Most dangerous of all are New Year’s Day and the US Independence