Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • STRABAG reports satisfactory financial performance
    February 22, 2016
    Construction firm STRABAG says that its performance in the 2015 financial year was ‘satisfactory’ and that its outlook for 2016 is positive. “We closed an overall satisfactory year in 2015 with a higher output volume on nearly unchanged employee levels and a lower order backlog. In 2016 we want to maintain the output volume at its high level and raise our EBIT margin to 3%. Thanks to our improved risk management and cost reductions, we are confident that we will reach this goal after having also succeeded i
  • Colombian road project complete
    December 14, 2021
    A major new Colombian road project is now ready for use.
  • Peru’s Matarani – Punta de Bonbon Highway
    January 5, 2016
    A major new highway project in Peru will improve connectivity for the Arequipa region - Mauro Nogarin writes Peru’s Matarani-Bonbon road project is an important route and forms part of the Camana - Dv Quilca - Ilo - Tacna highway project. The road stretches through several provinces in the Arequipa region. The deadline for completing the work is 720 days after January 2015, and it is scheduled to be completed by December 2016. Progress has been good and as of July 2015, it was 80% completed. The main
  • Proposed Slovakia tunnel project delayed
    October 4, 2016
    Delays seem likely for the project to build a tunnel link between Turany and Hubova in Slovakia. The 5.7km tunnel will form part of the D1 highway when complete but the construction schedule is being held back as the planned route runs through an aquifer area that provides water sources to three communities in the vicinity. A new route will have to be found so as to minimise the environmental impact. With the original timeline, construction of the tunnel could have commenced in 2017. But given the need to f