Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Tajikistan tunnel repair work
    February 11, 2021
    Repair work is planned for Tajikistan’s Istiqlol tunnel.
  • Black sea countries complete preparations for implementation of Black Sea Ring project
    August 23, 2016
    The Black Sea Ring Road project will improve transport connections for the region - Eugene Gerden writes. Russia has officially started implementation of a project, known as the Black Sea Ring Road, which involves building a four-lane highway system connecting the countries surrounding the Black Sea. The Black Sea Ring Road is a substantial project, a highway measuring some 7,140km in all. Among the countries participating in the project are Turkey, Georgia, Russia, Ukraine, Moldova, Romania, Greece and
  • New road project for Nicaragua
    August 19, 2016
    The World Bank looks likely to supply funding that will help pay for a major road improvement project in Nicaragua. The US$75 million loan should be agreed by November 2016, if all goes to plan. The funding will pay for major improvement works for the road connecting Nicaragua’s capital Managua with the country’s second city, Leon. At present the route suffers heavily from congestion at peak periods and is unsuited to the traffic volumes it has to cope with. The construction work is expected to commence in
  • Vietnam’s North-South Expressway sections
    March 24, 2025
    Key sections of Vietnam’s North-South Expressway are nearly complete.