Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Romanian highway works commencing
    July 15, 2022
    Highway works are commencing in Romania.
  • Road transport key to Africa's trade links
    February 17, 2012
    Road transport is the key to improving Africa's links within its own territory, and further afield as Patrick Smith reports. Development of road transportation is the key to the future of the African economy, and countries on the continent are making great strides. According to a report by a transport infrastructure expert at the New Partnership for Africa's Development (NEPAD), within the next 15 years the value of trade in Africa could reach US$250 billion if a $32 billion investment is made to integrate
  • Israel highIsrael highway franchise deal signedway franchise deal signed
    October 30, 2018
    A joint venture comprising Shapir Engineering and Impresa Pizzarotti has been awarded the franchise for Israel’s Highway 16. The deal is worth some US$275.6 million and involves building and operating the route over a 25-year concession. The package of works was awarded to the joint venture by the Israeli Government and the work involves building a 5km link that will join the existing Highway 1 with Jerusalem’s southern and western suburbs. The project also includes building two tunnels and three interchang
  • US$73 million Francis Scott Bridge replacement contract
    September 3, 2024
    Kiewit has been awarded a US$73 million Francis Scott Bridge replacement contract.