Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Colombia’s road development programme underway
    February 1, 2019
    Colombia’s 4G road infrastructure development programme is on track. The financing for 70% of this programme of works is now being secured. Worth some US$15.5 billion in all, the 4G programme is the fourth stage in the country’s plan to redevelop its transport infrastructure. Work commenced on the 4G programme in 2016 and it was originally due for completion in 2021. However, delays have crept into the programme due in part to issues surrounding the Brazilian contractor Odebrecht, which was handling some of
  • UK announces details of major road building programme
    December 1, 2014
    Details of a major programme of road building projects have been unveiled by the UK Government. The plan envisages some €18.83 billion (£15 billion) being spent on constructing new road links and upgrading existing routes. This is the largest single programme of works for the UK’s road network for several decades. The plan includes 100 major projects, perhaps the most notable being the long-awaited tunnel for the A303 past the Stonehenge archeological site. The existing route is narrow at this point and suf
  • SBM concrete plants for Fehmarnbelt tunnel
    June 17, 2021
    The 18km Fehmarnbelt Fixed Link in the Baltic Sea will create an uninterrupted traffic link between the Danish island of Lolland and the German Island of Fehmarn.
  • Colombia highway project – moving ahead as financing secured
    May 29, 2018
    The financing includes loans and funds and is being provided jointly by Colombia's national development bank Financiera de Desarrollo Nacional (FDN), Spain's Official Credit Institute (Instituto de Credito Oficial) and debt funds Ashmore-Caf and Blackrock.