Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Tunnelling conference and competition
    September 23, 2019
    The annual tunnelling conference and competition is due to take place in Miami from the 18th-20th November in Miami, Florida. The competition features eight categories and aims to identify the most important ongoing underground works and technologies that help cities change and enable habits and ways of life to evolve in order to build smart and sustainable urba
  • Asphalt airport runway refurbishment
    February 17, 2012
    Swedish contractor Peab Asfalt generally works on major road and highway projects in the inland portion of the country. However the company has shown itself able to take on a considerable challenge, by repaving an airport runway.
  • UK Government finalising plans for Stonehenge road tunnel
    January 12, 2017
    The UK Government is finalising its plans for the construction of a road tunnel close to the famous Stonehenge monument in Wiltshire. The 2.9km tunnel will carry the A303, a busy road that carries heavy traffic, particularly during the holiday season when large numbers of tourists pass through the area. The existing route passes close to the Stonehenge monument but the road is widely recognised as being unfit for purpose. As well as carrying cars, it handles a high percentage of large trucks, including heav
  • Transport the key to economic growth
    July 12, 2012
    Delegates from around the world discussed the future of global transport at the 2009 International Transport Forum in Leipzig, Germany In the face of the global economic downturn, transport will play a key role in supporting economic growth and in the creation of new confidence in the world's economic future, the delegates of the 2009 International Transport Forum (ITF) agreed. As almost all global threats have strong, central links and impacts, the transport sector will remain at the forefront of most glob