Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Busy bridge in Beijing replaced quickly
    March 31, 2016
    The replacement of a very busy road bridge in China’s capital Beijing has been carried out successfully. Due to the volume of traffic using the bridge during week days, the work had to be carried out quickly so as to minimise traffic disruption. But despite being carried out in the centre of Beijing, the replacement work for the Sanyuan Bridge just took 43 hours from start to completion.
  • Sacyr enters Paraguay road sector
    October 25, 2016
    Sacyr subsidiary Sacyr Concesiones is leading a consortium to will build and operate the Road 2 and Road 7 routes in Paraguay. The Road 2 route will connect Asunción and Coronel Oviedo. Meanwhile the Road 7 route will run from Coronel Oviedo to Caaguazú. Construction is expected to cost US$520 million with the concession package being for a period of 30 years. The Route 2 and Route 7 combined deal is of note as this will be Paraguay’s first PPP for a highway project. The consortium is headed by Sacyr Conces
  • Smart constructioon with GIS, GPS design technology
    May 2, 2012
    A UK highway project has benefited from the latest software, GIS and GPS technology, Mike Woof reports. Sophisticated software, GIS and GPS technology has played an important role in a large highway upgrade project in the UK and helping to increase efficiency and drive down construction costs.
  • Work starts on last Sofia-Kalotina section
    May 24, 2023
    Bulgaria’s A6 Europa Motorway from the capital with link up with Serbia’s A4 Motorway.