In Italy an MP1000 cutting system from Simex has been used to help resurface the walls of a highway tunnel. The SS51 State Road crosses through the Dolomites in the north-eastern Alpine Region of Italy. The SS51 starts in San Vendemiano in the province of Treviso and ends in Dobbiaco in the province of Bolzano and is a key road because it connects Cadore and the main towns in the area of Cortina d'Ampezzo. This 134.4 km road has expansion work and upgrades to improve safety and boost capacity.
December 3, 2014 Read time: 4 mins

 In Italy an MP1000 cutting system from Simex has been used to help resurface the walls of a highway tunnel. The SS51 State Road crosses through the Dolomites in the north-eastern Alpine Region of Italy. The SS51 starts in San Vendemiano in the province of Treviso and ends in Dobbiaco in the province of Bolzano and is a key road because it connects Cadore and the main towns in the area of Cortina d'Ampezzo. This 134.4 km road has expansion work and upgrades to improve safety and boost capacity.

One the most important sections is the 1.34km Caralte tunnel near Pieve di Cadore, which has a road surface 7.2m wide and includes 1.3m wide pedestrian walkways. Along with the ponte Cadore, this single-tube tunnel is part of an important bypass that avoids motorists from having to pass through the town of Perarolo di Cadore and the section of road known as la Cavallera with its many hairpin turns. But, completed in 1985, the concrete lining of the tunnel had started to deteriorate.

The ANAS road infrastructure authority of the Venice district decided to restore the tunnel walls by means of waterproofing and ceiling reinforcement. The project consisted of injecting polyurethane resins to close the cracks and prevent water from reaching the lining, removing 30mm of the degraded layer by scarification and then applying a special fibre-reinforced grout. The tunnel ceiling was also fittted with four L-shaped elements at spaced intervals to prevent detachment of the concrete over time. The rehabilitation works of the Cadore Tunnel were assigned to a temporary consortium made up of Cadore Asfalti Srl of Perarolo di Cadore and Esposito Mario of Trento.

A critical aspect of the job came from the time restraints of closures for the restoration works. Even partial closure would lead to detours along the long and winding roads. High productivity as well as precise profiling were crucial and in all, the project required a total of 24,300m2 of scarified surface.

Contractor Grotti carried out the scarification using a GTF 200 RC and a special Simex MP 1000 planer. The GTF 200 RC is a machine constructed by Grotti based on a tracked excavator but with features such as a telescopic boom that can follow the profile of the tunnel from the ceiling along the side walls; a hydraulic circuit designed to power the Simex attachments; and a remote control allowing the operator to work at a distance. Grotti was subcontracted by Cadore Asfalti. The extension of the boom right up to the 6.6m high tunnel ceiling and the fact that the boom could be retracted to follow the profile along the side walls allowed the work to be carried out. The Simex MP 1000 planer featured a drum equipped with 134 teeth, providing a surface ready for the application of the fibre-reinforced grout.

Injected resins were used to close the cracks and seal the joints. This entailed the use of single-component hydroreactive and expanding polyurethane resin from the MasterBuilder line produced by BASF. The MasterRoc MP 355 1K DW material is free of solvents and can react with water by forming a porous foam with expansion capacity 20-25 times its own volume.

This was injected in proximity to the cracks by boring 10-15mm diameter holes. Injection was carried out using polyamide truncated cone-shaped packers, and in some more critical areas, in steel as well. Both models were certified to withstand an injection pressure of 250bar and to ensure a seal. In some areas the procedure involved filling actual cavities formed behind the lining. In total, over 30,000 boreholes and injections were carried out, sealing the tunnel effectively.

Related Content

  • Upbeat in Beijing for BICES number 15
    January 22, 2020
    This year’s BICES exhibition in Beijing showcased much machinery destined for export to emergent countries that are taking advantage of China’s Belt and Road Initiative
  • BASF to boost output
    February 17, 2012
    BASF is boosting output at its Norwegian plant at Granerud in Nord-Odal. The €e1 million investment at the BASF Construction Chemicals facility will help develop production capacity for its MEYCO chemicals and MEYCO equipment lines, which are sold into the tunnel construction sector.
  • Airport runway rebuild at Bologna
    May 15, 2019
    Rebuilding a runway requires special attention to detail to maximise efficiency and safety Airport runways face special challenges with regard to the loads they carry on a daily basis, particularly when aircraft are landing. A modern jet aircraft will typically land at speeds of around 240-260km/h, with a laden 747 weighing as much as 265tonnes at the end of a long flight. The stresses these large aircraft place on runway surfaces are enormous and not just with the massive impact forces exerted during
  • Extraction operation benefits from haul road improvement
    May 23, 2014
    The trial of a novel compound at a site in Chile has shown how structural improvements can be achieved for dirt road applications Although the Barrick Gold Pascua Lama operation is a surface mining site, the experience with this technology is equally applicable for use on haul roads in large quarries or for dirt roads expected to carry heavy loads. This is of particular importance for transport in remote areas where large loads such as pre-cast bridge sections or girders for example may have to be carrie