RMD Kwikform: the role of temporary works in the age of BIM

Formwork and shoring are no longer isolated services that stand outside the design process of infrastructure projects, as Simon Dowd* explained In recent years, the roles of suppliers have changed as client and main contractors require more visibility and data from their construction sites. Due to the requirements of BIM - building information modelling - and the adoption of digital processes, it is no longer the role of a temporary works business to simply provide formwork and shoring. Simon Dowd said
April 19, 2018 Read time: 4 mins
Formwork and shoring are no longer isolated services that stand outside the design process of infrastructure projects, as Simon Dowd* explained


In recent years, the roles of suppliers have changed as client and main contractors require more visibility and data from their construction sites. Due to the requirements of BIM - building information modelling - and the adoption of digital processes, it is no longer the role of a temporary works business to simply provide formwork and shoring.

Simon Dowd said, “At 319 RMD Kwikform, it is now our responsibility to interact with the entire supply chain to support the overall method of construction, including its design and processes.”

He continued, “We recognised some years back that the industry would move away from 2D drawings. It has been a slow trend. But as we work closer with customers, particularly on larger infrastructure projects, it’s clear that 3D drawings should now be standard practice. We quickly learned that in order to service our customers - and by extension their clients - better, we must evolve and work smarter alongside them.”

RMD Kwikform has since evolved its 3D capabilities and designed solutions to automate highly realistic rendered 3D models, using an in-house developed visualisation tool, LocusEye. These models can be viewed on a PC, iPad or mobile phone, providing customers with a realistic model of how any solution looks on site. Flexible in functionality, LocusEye allows for changes to be made instantly and for solutions to be re-examined.

The industry needs smart solutions. With the growing adoption of BIM and the mandatory use of it in major projects, our customers are now demanding IFC BIM compliant models of our temporary works solutions.

Dowd said, “In response to our customer’s needs, we’re now building, automating and converting 3D AutoCAD models into IFC BIM compliant models. Through this system, on-site clashes can be detected, plus data can be captured to better manage equipment and plan construction phasing.”

LocusEye has already been used across a number of national and international projects. These include the UK’s Mersey Gateway and University College London Hospital, Australia’s Ventilation Facility and a number of access towers in Saudi Arabia.

Dowd said, “Some of the feedback we’ve already had is around the responsiveness of the models and how easy they are to interrogate. However, more importantly we’ve seen how much a positive impact this has had in allowing main contractors to visualise the overall management, build ability and future planning of the site.”

He continued, “Any construction site needs to be flexible; it’s just the nature of the job, the site demands change. With BIM compliant models and through LocusEye, our customers see what impact said change will have on a site.” How does this change and affect planned phasing; how does it impact delivery of equipment? He explained, “As the models are already embedded into the BIM model, our customers are able to manipulate processes, change phasing, and target specific elements of any model. This puts the control back in the contractor’s hands and grants complete visibility.”

“With BIM compliant packages and the added advantage of LocusEye, customers use their own tacit knowledge to look at practicalities for delivery, erection and dismantling of kit. They can see where access and egress can be placed and how the temporary works solution accommodates for other works on site.”

He concluded, “It’s all about the better management of the site in order to ensure even safer working practices, and ultimately reduce time and costs.”

*Simon Dowd is major projects manager at RMD Kwikform.

For more information on companies in this article

Related Content

  • Better asset management will reduce costs and improve efficiency
    August 22, 2013
    The FEHRL Infrastructure Research Meeting 2013 (FIRM 2013) raised key issues in transport innovation The key theme for FIRM 13 was advanced and innovative construction and maintenance, highlighting the importance of efficient asset management. Infravation, or infrastructure innovation, was another focus area for the event. Joris Al, FEHRL president said, “We aim to bring interested parties together. We’ve decided to build on existing knowledge rather than starting with front edge technologies and working
  • Users will drive investment policy, say keynote speakers at PPRS 2018
    March 26, 2018
    The world’s highway networks are facing “a major paradigm shift” from a past that was based on hardware, engineering, economic, analogue, vehicle and supply driven solutions to a future that will be based instead on software, social, environmental, digital, multi-modal demand-driven solutions. Think road users and the customers first if you want to help drive future road policy said Young Tae Kim, secretary general of the International Transport Forum (ITF), speaking at the opening ceremony of PPRS 2018
  • Merseylink wins US$3.12bn Mersey Gateway Project contract
    June 20, 2013
    Merseylink was today announced as the preferred bidder for the US$3.12 billion (£2bn) Mersey Gateway Project in North West England. Making the announcement together in the observatory in the Catalyst Museum in Widnes overlooking the River Mersey, Halton Borough Council and Merseylink also confirmed they have jointly identified savings amounting to “tens of millions of pounds” on the projected public sector contribution to the project budget.
  • Epiroc looks to the future following resilient 2020 trading
    March 12, 2021
    Epiroc CEO and president Helena Hedblom said the Swedish mining, quarrying and construction equipment manufacturer is well placed for good business in 2021 after resilient trading during a heavily COVID-19 disrupted 2020.