Flyover removal completed successfully

The removal of a flyover in Perry Barr, Birmingham, has now been completed in the UK. The work was carried out successfully by the contractor Tarmac within a tight timeframe
May 14, 2021 Read time: 2 mins

 

The 50-year-old flyover carried the busy A34 and was safely removed in just a single weekend to make way for an improved road layout. The work marks a key stage in Phase 2 of the A34 Perry Barr highways improvement scheme.

Extensive planning was needed for the job to be carried out safely. The highways scheme forms part of a £500 million regeneration project to transform Perry Barr and surrounding areas.

Working alongside specialist subcontractor S Evans & Sons Demolition, principal contractor, Tarmac employed seven excavators to remove the flyover.

Hitachi excavators were amongst the machines used for the work. These were fitted with demolition attachments to crush and remove the concrete superstructure and to cut through the steel supports. Over 300 lorryloads of materials were removed from the site, with all of the waste steel and concrete being recycled. The Tarmac team was able to minimise traffic disruption by removing the flyover abutments as well as the spans in one go.

With only one weekend allocated for the work, careful coordination of traffic was critical to the job. Transport for West Midlands (TfWM), working closely with Tarmac and the City Council, led in the organisation and communication of statutory diversion routes. The network was closely monitored through the Regional Transportation Coordination Centre to keep local residents, businesses, commuters and visitors informed of live traffic updates, road closures and alternative methods of travel.

Phase 2 of the A34 Perry Barr highways improvement scheme is set to complete in May 2021. Tarmac is now planning lifting precast sections of a new bridge onto the redesigned Birchfield Junction nearby within the next few weeks.

The wider programme of Perry Barr highway improvement works is set to be completed at the end of this year and will see local roads remodelled and redesigned to make the area more accessible by sustainable forms of transport including a new bus corridor.

The highway scheme will support the delivery of new homes, improvements to public transport, walking and cycling routes, new community facilities to make Perry Barr one of the most well-connected areas in the West Midlands.

For more information on companies in this article

Related Content

  • PERI’s balancing act at the Harpe Bru Bridge in Norway
    May 24, 2016
    Plans for the European Route E6 expansion in Norway include the 320m-long Harpe Bru Bridge over the Gudbrandsdalen Lågen River, at Sør-Fron in Oppland province. For the superstructure, PERI civil engineering technology experts developed a balanced cantilevered solution based on the VARIOKIT Engineering Construction Kit. Statens vegvesen, Norway’s agency for public road building, selected an extradosed cable-stayed bridge design – the first such bridge in Norway. It combines the load-bearing behaviour
  • VIDEO: Gap closed for Gordie Howe Bridge
    July 26, 2024
    A 26m gap in the deck was recently closed on the bridge that will connect Detroit in the US state of Michigan and Windsor in the Canadian province of Ontario.
  • Ground penetrating radar used to investigate tunnel deterioration
    May 13, 2015
    Using ground penetrating radar to determine reason for serious pavement settling in Kentucky-Tennessee tunnel Just a few years after the opening of the Cumberland Gap Tunnel, highway officials noticed moderate to severe settling of the continuously reinforced concrete pavement. The mountain tunnel provides an important link between Kentucky and Tennessee along US25E and the problem looked serious, with many voids discovered beneath the pavement surface. To investigate the problems, the Kentucky Transpor
  • Hydrodemolition equipment helps Swiss bridge rebuild
    December 2, 2014
    A highway bridge in Switzerland has been refurbished with help from hydrodemolition equipment supplied by Aquajet The firm’s latest Rotolance 2500 was used alongside an Aquacutter 710 VE evolution on the Viaduc de Chillon link, above Lake Geneva. The machines were used by Zurich-based hydrodemolition specialist contractor, Walo Hydrodynamik, to remove more than 25,000m³ of concrete deck on the bridge.