Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • XCMG cranes aids in key Chinese bridge construction
    June 10, 2015
    Work to construct a key bridge in China has been aided by a crane supplied by XCMG The crane was used to erect 100m high twin bridge supports for the structure. The bridge is a dual-cable, pre-stressed concrete cable-stayed bridge featuring two towers. The bridge is located in Shandong and was recently opened to traffic. The project was not without its challenges. Building such a large bridge spanning the Yi River required sophisticated methodologies and use of the latest technology. Mounting the cab
  • Mobile grouting trailers for soil nail rigs
    February 7, 2012
    Geotechnical specialists, Bachy Soletanche and Carillion Piling are currently working on an £18 million (e21 million) geotechnical contract as part of carriageway improvements on the M1 motorway to the north of London, England. The work between junctions 10-13, Luton to Milton Keynes, is being carried out for the Costain Carillion joint venture working on behalf of the Highways Agency. The piling and soil nailing works are to facilitate the conversion of the current hard shoulder to a peak-time running lane
  • Second giant moveable scaffolding system set for Mersey Gateway
    May 4, 2016
    A second movable scaffold system (MSS) is on its way from China to the UK town of Halton, as part of the Mersey Gateway Project, a toll bridge over the Mersey River in England. The machine will be used to build the south elevated approach viaduct that will connect the main road network in the town of Runcorn to the Mersey Gateway Bridge, now under construction.
  • Lindsay argues the case for reversible lanes over adding lanes
    June 26, 2018
    Build new lanes or use existing lanes more effectively? In a recent US study* commissioned by Lindsay Transportation Solutions, the company argues the case for reversible lanes. The level of future uncertainty in transportation planning - specifically in addressing congestion on urban freeways - has increased significantly over the past few years. The impact of connected and autonomous vehicles on traffic flow, of Mobility as a Service (MaaS) initiatives, particularly the car-sharing elements, and exciting