Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Manitowoc’s in demand in Oz
    May 14, 2014
    Leading Australian crane rental firm Universal Cranes has built two bridges using Manitowoc cranes from its fleet. The company used Manitowoc’s largest all-terrain crane, a GMK7450, for the first job and selected two Manitowoc crawler cranes – a 16000 and a 12000 - for the second. Key to the speed of the two projects was the cranes’ quick set-up and precise load control, as well as Universal Cranes’s specially-designed lattice spreader, as Nick Morris, engineering and sales manager at Universal Cranes, e
  • We can be Heroes
    January 11, 2023
    Paraguay’s Puente Héroes del Chaco will provide a vital transport link for the country once it is complete, Mauro Nogarin and Mike Woof report
  • Heavy work for Cat 730C Ejector Truck on English bypass
    December 18, 2017
    When Flannery Plant Hire was awarded work on the Norwich bypass project, they purchased a wide range of new Caterpillar machines. Caterpillar dealer Finning UK & Ireland supports construction of the Norwich Bypass, one of the UK’s largest road infrastructure projects, with a vast range of Caterpillar machines and advanced Caterpillar Production Management - CPM. Known as the Northern Distributor Road, the project is managed by primary contractor Balfour Beatty, with P. Flannery Plant Hire as main earthwork
  • Tenders open for England’s A66 northern trans-Pennine route
    October 31, 2019
    A €52 million contract to design the transformation of the A66 northern trans-Pennine route in England is now up for grabs, according to Highways England. A tender is open for dualling the remaining single carriageway sections of the A66 which links the M6 motorway at Penrith in Cumbria and the A1(M) motorway) at Scotch Corner in North Yorkshire. The formal notice for the A66 Preliminary Designer, Construction Technical Advisor and Supervision tender process has been published in the Official Journal of