Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Parts delivery
    February 29, 2012
    Komatsu Europe has invested in developing an efficient spare parts operation - Mike Woof writes. Komatsu Europe is reaping the benefit of its investments in the spares support facility in Belgium. During the financial crisis new machine sales plummeted across Europe for all manufacturers but Komatsu Europe was able to ensure steady income through its spares support service. With many European customers holding onto machines longer during the last few years due to the downturn, spares support has been pivota
  • Strong interest for construction equipment show
    February 21, 2012
    Most of the major manufacturers of extraction and crushing equipment worldwide will be present at the upcoming Hillhead show, either directly or through local distributors. Set in a working quarry, the Hillhead exhibition has set a lead for the quarrying sector. An industry only show, the event is being held this year at the Hillhead Quarry, Buxton in the UK on 22-24 June.
  • Strong interest for construction equipment show
    May 2, 2012
    Most of the major manufacturers of extraction and crushing equipment worldwide will be present at the upcoming Hillhead show, either directly or through local distributors. Set in a working quarry, the Hillhead exhibition has set a lead for the quarrying sector. An industry only show, the event is being held this year at the Hillhead Quarry, Buxton in the UK on 22-24 June.
  • Colombia concrete casting construction
    May 10, 2018
    Spanish specialist supplier Moldtech is supplying a concrete precasting plant to a customer in the Colombian city of Medellin. The deal is for the design, manufacture and commissioning of a complete factory for the production of bridge girders and precast concrete frames. This follows a visit by a technical team from Moldtech to Medellin to show the client its latest precast concrete plant technology. The new plant being erected will allow the client to supply bridge girders up to 45m in length and 2.2m