Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Key Florida highway link wins major award
    July 2, 2014
    A major highway connection project located in Tampa, Florida has won a 2014 Outstanding Project Award from the Florida Department of Transportation (FDOT) and the Florida Institute of Consulting Engineers (FICE). The link was opened in January 2014 and was engineered by designer Atkins. The 1.6km-long I-4/Selmon Connector links I-4 with the Lee Roy Selmon Expressway. The US$425 million Connector now carries over 24,000 vehicles/day, which includes some 2,000 heavy vehicles/day. With the construction of the
  • Vögele MT 3000-2 for Austria A2 motorway
    May 14, 2014
    Road construction work with moving traffic always represents a major challenge. This is especially true when only one lane can be closed, consequently leaving little space for working and manoeuvring. That was exactly the case for a rehabilitation project on the A2 motorway in Austria between Vienna and Graz near Schäffern. However, the job was further complicated by another factor: all access roads to the job site were roughly 1km apart. Ensuring an uninterrupted supply of mix to the paver under these
  • Interest grows in Kaugummiasphalt cold mix from Macismo
    November 25, 2016
    Asphalt supplier BPH says Czech highway officials have been meeting with autobahn managers from Germany’s Leipzig region to discuss cold path repair methods on concrete surfaces. BPH, founded in 2013 in Königsbrück near Dresden in the states of Saxony, produces and sells Kaugummiasphalt and Macphalt, both products based on the Macfix Technology from Macismo.
  • Bridge improvements reduce flood threat
    February 16, 2012
    The impact of the new Eden Bridge over the River Eden on its flood plain is a key issue to the construction of the Carlisle Northern Development Route (CNDR).