Skip to main content

Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Manitowoc gets in the groove with new Grove rough terrain GRT8100
    March 15, 2016
    Manitowoc’s all-new GRT8100 launches the manufacturer’s Grove rough Terrain line. The 90tonne GRT8100 is an update of the RT890E and has a 47m boom with a maximum tip height of 49m. With a full complement of boom extension and insert options, the crane has a reach up to 77m. The boom is lighter and longer than its predecessor, but has the ability to lift heavier loads. “Customers will find the new crane more reliable thanks in part to our Product Verification Centre in Shady Grove, Pennsylvania, US,”
  • Manitowoc gets in the groove with new Grove rough terrain GRT8100
    January 6, 2017
    Manitowoc’s all-new GRT8100 launches the manufacturer’s Grove rough Terrain line. The 90tonne GRT8100 is an update of the RT890E and has a 47m boom with a maximum tip height of 49m. With a full complement of boom extension and insert options, the crane has a reach up to 77m. The boom is lighter and longer than its predecessor, but has the ability to lift heavier loads. “Customers will find the new crane more reliable thanks in part to our Product Verification Centre in Shady Grove, Pennsylvania, US,”
  • Sand, gravel and asphalt, building Poland’s roads
    February 24, 2012
    A new quarry is producing top quality aggregates for Poland's massive road construction programme writes Claire Symes. Wakoz Beton's Glazica sand quarry in Poland is a major source of high quality sand and gravels for the Gdansk construction market. The site is modern and only opened in 2006 but Wakoz Beton has continued to invest in facilities to improve its efficiency and output quality. The installation of a CDE mobile washing plant at the site last year is allowing it to provide materials for concrete.
  • Aggregate Industries opens second Manchester concrete plant
    September 12, 2019
    Aggregate Industries has opened its second ready mix concrete plant in Greater Manchester, England. The company says the move has been made to cater to rapidly growing demand in the area. The new high-capacity site – located just off the M56 in Wythenshawe – is situated between Manchester city centre and Manchester Airport. Aggregates Industries says both areas are currently undergoing a high volume of significant improvement works that require an extensive amount of concrete, including the constructi