Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Goldhofer’s new trailers offer mobility
    April 9, 2018
    Goldhofer claims that its latest heavy equipment trailers offer versatility for construction industry logistics. The firm’s proven and innovative transport solutions are said to meet demanding requirements. One of the innovative systems is the ADDRIVE 6, a six-axle version of a revolutionary transport solution. This system offers a combination of trailered and self-propelled modules in a single vehicle. The firm says that the ADDRIVE system can handle a wide range of cargos efficiently and this package can
  • Fast resurfacing work in UK by contractor Eurovia
    May 15, 2017
    In the UK the contractor Eurovia has recently carried out a challenging resurfacing job within a tight timescale. The firm had to contend with live traffic on a busy stretch of motorway, while carrying out the work close to shared intersections. The traffic was particularly heavy also during part of the job due to a holiday period and large numbers of tourist vehicles using the stretch of motorway.
  • Fluor wins award from Highways England
    November 5, 2015
    Fluor Corporation has won an achievement award from Highways England for its National Roads Telecommunications Services (NRTS) project. This has been recognised by Highways England for achieving 3 million safe working hours while executing the project across England’s operational motorways and trunk roads. The Significant Achievement Award for Safety was presented by David Brewer, Highways England’s network delivery and development executive director to Kevin Hamer, Highways England NRTS contract manage
  • Overlay extends bridge's life
    July 24, 2012
    More than 3,000 vehicles a day pass over the US-95 Bridge over Lake Creek near the Coeur D'Alene Tribal Casino in Worley, Idaho, USA. The original deck, built in 2007, was poured concrete with a micro-silica layer added for protection. A QTT weather station with FreezeFree anti-icing technology is mounted in the bridge rail. With big variances in temperature and a lot of wind in this region, the original deck material became thick causing a near 80m length of micro-silica to over-harden. Idaho DOT engineers