Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Storstrom Bridge to be Denmark’s third longest
    March 8, 2018
    Form and functionality come together in Denmark’s latest Storstrom Bridge design. David Arminas reports. An Italian joint venture recently won the construction contract for what will be one of Denmark’s longest bridges, the replacement 4km-long road and rail Storstrom Bridge. The Danish Road Directorate - Vejdirektoratet - awarded the work to a joint venture of Condotte and Grandi Lavori Fincosit along with bridge design consultant Seteco Ingegneria as a subcontractor. Estimated cost is around €550 milli
  • Eradicating work zone danger
    June 26, 2013
    New safety systems for highway work zones are helping to reduce deaths and injuries in the United States, while much work is being done in Europe to improve work zone safety. Guy Woodford reports. With more road building underway than at any one time in Texas history, the US Lone Star state’s Department of Transportation (TxDOT) is introducing its first highway safety system with queue-warning technology and temporary rumble strips to cut work zone collisions. Debuting along a central Texas stretch of the
  • Keestrack’s growing presence in China
    November 21, 2018
    Keestrack is introducing a comprehensive range of large tracked mobile machines to the Chinese market. These encompass all relevant screening and crushing technologies for quarrying, recycling and aggregates industry sectors. Four important new models are being unveiled. The B4 jaw crusher ensures less wear and better crushing capacities due to its double-deck vibrating pre-screen (2300 x 1000mm). The proven 1100 x 700mm jaw crusher (maximum feed size 600mm) reaches an hourly output up to 400tonnes and pro
  • Expressways upgrades for key UK routes
    December 15, 2017
    Key routes in England are to be upgraded as part of a programme of works worth a mighty €33.9 billion (£30 billion) plan from 2020 to 2025. This five year plan from Highways England will see many of the major A road routes being reclassified as A(M) expressways. These will resemble motorways in many respects, with new on and off ramps and additional lanes being constructed. The A14 stretch between Cambridge and Huntingdon will be one of the first stretches to be upgraded in such a fashion. This is an