Runway resurfacing in Brussels

Years of heavy use meant that runway 25 at Brussels Airport required attention, with a full resurfacing needed. Smooth runways are vital for large international airports as they optimise safety and reduce wear and tear on expensive aircraft, in addition to boosting comfort for airline crews and passengers.
April 2, 2021 Read time: 3 mins
Using the Topcon 3D tools allowed the work to be completed ahead of schedule, while delivering the high quality required for the airport runway

The 3.3km-long by 45m-wide runway 07L/25R at Brussels Airport was in need of a complete renovation. High usage meant that this renovation would have to be conducted quickly, accurately and safely. The airline authorities brought in general contractor Willemen Infra to handle the project, with the specialist sub-contractor Top-Off being brought in to handle the milling work.

Despite numerous challenges facing the project, not least the constraints associated with minimising airline disruption, the runway was ready for operation again in just over one month.

Phillipe Grevendonck, project development manager at Topcon, said: “When Top-Off asked us to assist with this renovation project, we didn't hesitate. The time pressure was high, because the runway closure had to be kept to a minimum. The quality requirements were, of course, exacting: the runway must ensure safety, and we had to extend the life of the asphalt layer by preparing a flat foundation and ensuring an optimal milling finish.

“We helped Top-Off with the preparation and start-up at the worksite, as well as with the calibration of the machines. Where necessary, we also carried out the position checks, because milling requires precision, whilst remaining on standby during the work, to support Top-Off as necessary.”

The volume of milling was significant. John Vastmans, CEO of Top-Off explained “We placed two new layers of asphalt on the runway, which amounted to 222,000m2 and about 60,000tonnes.  The work had to be 90% done in just five days. That is to say: we milled at a rate of more than 10,000tonnes/day.”

Top-Off’s team started by milling the old asphalt layer off the runway in order to apply the new asphalt onto an optimal terrain model. Grevendonck explained: “The 3D model supplied by Brussels Airport Company ensured the best possible sub-foundation for the new asphalt layer.”

Precision milling using the Topcon 3D systems was carried out to provide an accurate base to lay the new asphalt layers on top
Precision milling using the Topcon 3D systems was carried out to provide an accurate base to lay the new asphalt layers on top

When it came to milling, Topcon’s 3D millimeter GPS system had an impact on the efficiency of the project. The solution combines the advantages of laser and GPS systems.

Vastmans said: “With millimetre GNSS, we had the advantage that all the machines could make use of a single laser, which not only made the system easy to use but also saved costs.”

“If the laser beam is interrupted, the system can continue to operate for about four seconds based on its last corrections. If it takes longer before the obstruction clears, the use of the rotating laser allows a connection to be established again. The biggest advantage of this is the huge time savings. In the vertical plane we have a 10m window in which we can work with a single laser. So, in that regard, we have almost no restrictions.”

Vastmans added: “Repaving with new asphalt had its challenges too, mostly because at the Brussels Airport worksite there was non-stop movement.”

Grevendonck elaborated “There was a point where there were 20 excavators, 30 dump trucks, 20 trailers and five milling machines all there at the same time. There were always five lasers set up on the project. All machines could select a laser of choice within reach. One laser could give guidance to multiple milling machines simultaneously."

Work also had to be conducted on the sewer pipes, which imposed an even tighter deadline. Vastmans added “With the solutions utilised, milling out of the contours for the sewer basins also went smoothly.”  

With the help of Topcon’s MM GNSS system, the project was completed ahead of schedule. “It went very well,” said Jan Eikenaar, site manager for Top-Off. “We finished ahead of schedule. That’s always a favourable position to be in. The customer is very satisfied. Our work was grade-checked, and we remained well within the error margin.”

For more information on companies in this article

Related Content

  • Sandvik’s DT1131i jumbo and iSURE software in Iceland and Norway
    August 14, 2019
    Sandvik’s DT1131i three-boom, electro-hydraulic jumbo, iSURE tunnel management software and the latest drill bit hardware were recently put to the test in Iceland and Norway* Czech contractor Metrostav recently achieved 105m of tunnel excavation in a record-breaking six days. But it will be consistent performance and progress that will see Iceland’s Dyrafjordurgong Tunnel in the remote Westfjords region open on time and on budget. The 5.3km Dyrafjordurgong Tunnel is costing around €69 million and due
  • Volvo CE stages successful six-site paving demo
    April 11, 2013
    Volvo Construction Equipment’s (CE) dealer in the Netherlands, Kuiken, recently hosted a live, five-day demonstration program using a Volvo P7820C ABG paver machine. On a road trip across the country, the Kuiken team visited six different customers, travelling more than 1,700km in total, and clocking up more than 60 hours of paving. “We wanted to test how the market and existing customers, as well as potential ones, would react to the Volvo P7820C ABG machine,” says Arjen Mostert, sales & support manager of
  • Bentley advances construction software technology
    December 19, 2016
    Design and construction software specialist Bentley Systems is strengthening its position in the market with the introduction of new software advances as well as a series of strategic business moves. This allows the company to offer new solutions and technologies to its client base, as well as reaching out to new business segments The firm is introducing an array of powerful tools to the market. A key launch is for the OpenRoads Designer CONNECT Edition, which is the successor to Bentley’s well-proven an
  • JCB’s Hydradig 110W proves revolutionary for French Contractors
    August 10, 2018
    The versatility of JCB’s Hydradig has landed the machine a role in a demolition application in the centre of Coventry city. The JCB Hydradig 110W was purchased by Rugby-based French Contractors, which is carrying out the project on behalf of Jackson Civil Engineering. The unit is assisting in the strengthening and rebuilding of Swanswell Viaduct between junctions one and four on the A4053, Coventry’s ring road. It is maximising an array of attachments including a Powertilt tilting hitch, a full range of