Premium ponds

A series of balancing ponds are being used to create a sustainable drainage solution on the Highways Agency’s £375m 28km dual carriageway extension of the A46 in Nottinghamshire. Fearing that a doubling of the surface area of the Newark to Widmerpool trunk road would create excessive high surface water runoff, principal contractor Balfour Beatty and their consultant engineers, URS Scott Wilson, designed 12 balancing ponds, with the outfall from each controlled by Hydro International’s Hydro-Brake Flow Cont
April 25, 2012 Read time: 2 mins
A series of balancing ponds are being used to create a sustainable drainage solution on the 2309 Highways Agency’s £375m 28km dual carriageway extension of the A46 in Nottinghamshire.

Fearing that a doubling of the surface area of the Newark to Widmerpool trunk road would create excessive high surface water runoff, principal contractor 1146 Balfour Beatty and their consultant engineers, URS Scott Wilson, designed 12 balancing ponds, with the outfall from each controlled by 1402 HYDRO International’s Hydro-Brake Flow Control devices.

2759 Environment Agency guidelines require flow restrictions to be held at the predevelopment rate for greenfield runoff, to channel water volumes into local watercourses and control water quality. The A46 also lies adjacent to several environmentally, agriculturally and historically sensitive locations as well as within the flood plains of the Rivers Trent and Devon.

Designed with a permanently wet sump area, the balancing ponds also feature vegetated dry sections to ensure maximum entrapment of debris and silt at most stages of inflow. The outflow of each pond is fitted with a Hydro-Brake Flow Control or chamber, depending on maximum design flow required, from 27.5 to 66 litres/sec.

Work on the A46 upgrade scheme began in 2009, and is due to be completed in summer 2012. It is expected to improve traffic flow and
safety, while by-passing several villages.

For more information on companies in this article

Related Content

  • Hoover Dam’s innovative new bridge bypass
    April 12, 2013
    Soaring over 271m above the Colorado River, the Hoover Dam Bypass overlooks one of America’s greatest icons and assets. The October 2010 opening of the bypass improves the security of the historic Hoover Dam by removing through traffic from US Route 93. This has reduced its vulnerability to a terrorist attack against an international landmark and guarded the most sustainable source of electricity and the scarce water supply for the entire southwestern United States. By diverting traffic from the hairpin tur
  • Earthmoving machines the backbone of construction
    February 7, 2012
    Earthmoving machines remain the backbone of construction operations - writes Mike Woof. ADTs, excavators and wheeled loaders play pivotal roles in most construction jobs with the earthmoving stage providing a key component of most projects.
  • LagoonHull project put on hold
    February 8, 2023
    The plan by the UK city of Kingston upon Hull is to transform the city centre and river frontage running from the 2.2km-long, single-span suspension Humber Bridge.
  • Ciber discusses optimizing asphalt mixes
    December 19, 2017
    A good quality mix plays an important role in road construction and the asphalt manufacturing process starts with the mix design in the laboratory, which takes place under controlled conditions and depends on the materials available locally. A mix design that matches the plant's limitations has a higher probability of success. The properties of the aggregates, such as water absorption, abrasiveness, and the equivalent sand index, may influence the quality of the mix produced in the plant. In the laboratory