Paving an Iowa road

A slipformer from Power Pavers has been used to pave a road stretch in Iowa.
By MJ Woof February 4, 2025 Read time: 2 mins
Equipment from Power Pavers helped a contractor complete a paving job in Iowa ahead of schedule


Specialist firm Jones Contracting Corporation won the contract for paving nearly 4km of county road adjacent to the Lee County Fairgrounds in Iowa earlier this year. The firm knew meeting the schedule would be critical as the road would be a crucial link for the upcoming county fair. Some 15,000 people were expected.  

The project schedule established by Lee County was for the work to be completed in 35 working days. However, Jones Contracting completed it in just 25 ½ days.

The project, along the Business Route of County Road 218, ran from just north of the town of Donnellson to the county fairgrounds, then jumped to the south of the town. Overall, it included 3.8km of 102mm concrete overlay on top of the existing asphalt roadway, as well as 10 driveways and installation of new shoulders. The work was done in May, ahead of the heaviest heat of summer when the heated asphalt of the existing pavement might be problematic.

For the Lee County Overlay Project, both of the company’s Power Paver SF-1700 and SF-2700 slipform pavers were used. The company also has a TC-2700 texture/curing machine and a Power Curber 5700-D curb and gutter machine.

Upon completion of the job, Jones Contracting only had to grind the concrete at three headers, indicating that the concrete was smooth and required minimal reworking.

The company has been in business for ten years, and Patrick selected Power Pavers for his choice of machinery early on. “We’re extremely happy with Power Pavers. They are really great people to work with. They are located just up the road in Cedar Falls, so getting parts is easy,” said Patrick, adding, “And the machines they build are reliable and built to last.” 

 

 

For more information on companies in this article

Related Content

  • Fehmarn Belt Tunnel opening set for mid-2029
    August 16, 2024
    Around 1,500 tonnes of reinforcement for casting the concrete tunnel elements are produced weekly for the 17.6km Fehmarn Belt Tunnel that will connect the Danish island of Lolland with the German island of Fehmarn.
  • Cold winters ravage roads requiring repairs
    January 7, 2015
    Detroit is one of the three worst cities in the US for poor weather, along with Chicago and Toledo For Metro Detroit the winter of 2013-14 was the second snowiest season on record, bested only by the winter of 1880-1881. This had a terrible effect on the city’s roads and in the suburb of Southfield, officials assessed the poor state of the asphalt and concrete streets and realised the conventional patch and fill programme would not be sufficient.Instead the contract was modified to cover mill and resurfacin
  • US RCC paving job carried out with Volvo CE machines
    October 21, 2016
    US contractor Conewago Enterprises is using a paver from Volvo CE to lay a roller-compacted concrete (RCC) surface at the Liberty Trust distribution centre in Shippensburg, Pennsylvania. This facility lies close to Interstate-81, which runs through the Appalachian Mountains from the Canada-US border to Tennessee. This 1,376km route carries heavy truck traffic and as a result, hundreds of distribution warehouses have being constructed along the route of this busy transport corridor. Conewago Enterpris
  • Wirtgen Group machines delivering new runway for German airbase
    October 26, 2016
    Machines from the Wirtgen Group are carrying out an important reconstruction job for the surface course at Büchel Air Base. Road machinery from Hamm, Vögele and Wirtgen as well as asphalt plants from Benninghoven have been carrying out the work, delivering a new runway within a tight timeframe. To achieve this, the work had to be planned well in advance, with the contractors organising the logistics and their personnel accordingly.