Paving an Iowa road

A slipformer from Power Pavers has been used to pave a road stretch in Iowa.
By MJ Woof February 4, 2025 Read time: 2 mins
Equipment from Power Pavers helped a contractor complete a paving job in Iowa ahead of schedule


Specialist firm Jones Contracting Corporation won the contract for paving nearly 4km of county road adjacent to the Lee County Fairgrounds in Iowa earlier this year. The firm knew meeting the schedule would be critical as the road would be a crucial link for the upcoming county fair. Some 15,000 people were expected.  

The project schedule established by Lee County was for the work to be completed in 35 working days. However, Jones Contracting completed it in just 25 ½ days.

The project, along the Business Route of County Road 218, ran from just north of the town of Donnellson to the county fairgrounds, then jumped to the south of the town. Overall, it included 3.8km of 102mm concrete overlay on top of the existing asphalt roadway, as well as 10 driveways and installation of new shoulders. The work was done in May, ahead of the heaviest heat of summer when the heated asphalt of the existing pavement might be problematic.

For the Lee County Overlay Project, both of the company’s Power Paver SF-1700 and SF-2700 slipform pavers were used. The company also has a TC-2700 texture/curing machine and a Power Curber 5700-D curb and gutter machine.

Upon completion of the job, Jones Contracting only had to grind the concrete at three headers, indicating that the concrete was smooth and required minimal reworking.

The company has been in business for ten years, and Patrick selected Power Pavers for his choice of machinery early on. “We’re extremely happy with Power Pavers. They are really great people to work with. They are located just up the road in Cedar Falls, so getting parts is easy,” said Patrick, adding, “And the machines they build are reliable and built to last.” 

 

 

For more information on companies in this article

Related Content

  • Successful resurfacing at New York's JFK Airport
    May 3, 2012
    A huge logistics operation has been carried out successfully at New York's JFK Airport. One of the busiest runways at one of the world's busiest airports is now open to air traffic again, following a 120 day closure for resurfacing.
  • Ethiopia announces three road projects worth over $240 million
    April 17, 2015
    In Ethiopia, three road projects worth over US$240 million will be built as part of the country's fourth road sector development plan. The government will fund the projects using its own resources. The first project is the 83km Sodo-Tercha asphalt-concrete project, costing around $84 million and to be built by China Railway Seventh Group. Completion is scheduled for 19 months. The second project, worth $102 million is the 99km Bilbela-Sekota road project, scheduled to take 39 months and to be built
  • Diamond in the Pearl: China’s Hong Kong-Zhuhai-Macao Bridge complex
    March 8, 2018
    People in the Pearl River Delta are celebrating the Chinese New Year with the imminent opening of the Hong Kong-Zhuhai-Macao Bridge. David Arminas reviews progress. China’s Spring Festival, or Lunar New Year, is celebrated with the usual enthusiasm and spectacular fireworks. But celebrations will be particularly joyous for many people in the southern Pearl River Delta. The soon-to-be-open Hong Kong-Zhuhai-Macao Bridge (HZMB) will slash travel time between the Hong Kong Special Administrative Region, Zhuh
  • Hanoi’s new bridge and highway
    December 11, 2024
    Plans in hand for Hanoi’s new bridge and highway.