Kieswerk Kohler solves fines problem with M2500 from CDE

Following installation of the M2500 mobile washing plant, Kieswerk Kohler is said to have addressed the issues caused by excess fines in the material at their quarry in Engen / Welschingen, southern Germany. The solution offered by CDE has also enabled the production of an additional sand product which the company is now able to offer customers. The raw material processed by Kieswerk Kohler at the site contains a large proportion of material smaller than 250 microns. With the crushing and screening proce
September 26, 2013 Read time: 4 mins
Following installation of the M2500 mobile washing plant, Kieswerk 2278 Kohler is said to have addressed the issues caused by excess fines in the material at their quarry in Engen / Welschingen, southern Germany. The solution offered by 3168 CDE Global has also enabled the production of an additional sand product which the company is now able to offer customers.

The raw material processed by Kieswerk Kohler at the site contains a large proportion of material smaller than 250 microns. With the crushing and screening processes previously employed on the material, the sand was out of specification for use in concrete. “This was causing a problem as local concrete manufacturers are my main customers,” explained owner Thomas Kohler. “I had been working to develop a system which would allow production of concrete aggregates, especially sand, so that it would meet the requirements of the European standards. The solution offered by CDE has also enabled the production of an additional saleable sand product which I can now offer customers.”

CDE in Heimertingen was formed in December 2012 and represents a development of the previous distributor agreement that was in place for southern Germany with Jurgen Koelsch. Stefan Koelsch director of CDE said, “CDE gives washing a new focus in Germany. This ensures that we are able to offer aggregate and construction material manufacturers a level of washing expertise, as well as project management capability and service support that is only available when construction materials producers buy direct from the manufacturer.”

In seeking to address the issues raised by the large proportion of minus 250 micron material in the sand and gravel feed, Kieswerk Kohler were investigating the option of washing the material after the initial dry screening process. “We were thinking about several different options and ways in which we could correct the gradation curve of the sand in order that it met the required concrete specification,” said Kohler. “When we explained the issue to CDE they came up with a solution very quickly and, since it has been introduced, the plant is doing exactly what I wanted it to do.”

The processing system introduced by CDE in Baden-Wurttemberg includes the M2500 E4 mobile washing plant and the AggMax 83 portable logwasher. In addition to the problems caused by the excess fines content in the feed material, Kieswerk Kohler were also faced with clays and silts which the dry processing system was not able to effectively remove. The consultation between Thomas Kohler and Stefan Kolsch revealed that by introducing the AggMax the quality of aggregates produced would also be improved.

The sand and gravel feed is delivered to the M2500 washing plant by loading shovel and operates at 100tonnes/hour. The plant accepts 0-100mm material with a grid on the feed hopper rejecting any oversize. The feed material is then delivered to the M2500 aggregate screening phase which is achieved using the integrated Prograde P2-75 rinsing screen.

The top deck of this screen separates at +32mm and this material is sent to stockpile via one of the integrated wing conveyors. The bottom deck separates at 4-32mm and this material is then sent to the AggMax for scrubbing via the integrated Rotomax RX80 logwasher. Once material has been processed by the Rotomax it is discharged onto a triple deck horizontal sizing screen which classifies the aggregates into 4-8mm, 8-16mm and 16-32mm.

The 0-4mm material collects in the Prograde screen sump and is pumped to the integrated Evowash sand washing plant. The Evowash screen is split to allow the production of two sand grades – 0-4mm concrete sand and another 0-2mm product. “The creation of the additional 0-2mm sand product was required as there was too much of this material in the 0-4mm range. The sand washing phase is configured to remove up to 25% of the 0-2mm material from the 0-4mm product to allow for the production of concrete sand,” said Koelsch.

An additional benefit for Kieswerk Kohler has been the creation of this 0-2mm sand product which they have now found a market for.

As well as selling the final washed products to local concrete manufacturers in Germany some material is also exported into Switzerland due to the proximity of the Kieswerk Kohler site to the Swiss border.

For more information on companies in this article

Related Content

  • Preventing toxic run-off from roads
    May 15, 2019
    An innovative sustainable drainage material is said to offer a simple and versatile solution to removing toxic heavy metals pollution from highways. Developed by the water infrastructure systems provider SDS Limited, SDS Aqua-Xchange is a versatile and efficient granular material that captures copper and zinc in surface water runoff from motorways, trunk roads and other high-traffic areas. SDS Aqua-Xchange is an engineered treatment media that can be used to meet the UK’s Sustainable Drainage Systems (S
  • Advanced road recycling systems
    March 15, 2012
    Advanced road recycling capabilities are offered by Wirtgen. Having started as a contractor, Wirtgen’s roots in this side of the business are strong and the company’s development of road recycling systems has become a core competence, originating as an offshoot of its contract work. Wirtgen’s leading position in the milling machine market continues and although an increasing number of rival firms offer machines, the company’s share of this segment remains dominant. With demand for machines having grown in 2
  • Wirtgen going for growth
    May 28, 2012
    The Wirtgen Group has held a highly successful Technology Days event at the brand new Kleemann facility in Göppingen near Stuttgart. Some 2,600 people attended this year's event, the largest of the three held so far by the firm. A key focus for this year was highlighting the full integration of the Kleemann crushing equipment operation within the Wirtgen Group. The previous Technology Days events were held at the Hamm facility in Tirschenreuth and at the Wirtgen headquarters in Windhagen. Following the Kle
  • To re-use asphalt in quality mixes
    August 25, 2016
    Asphalt plant manufacturers agree that recycled asphalt is a valuable resource that is too good to waste - Mike Woof writes. Around the globe there is growing interest in the use of recycled asphalt pavement (RAP). The technology to utilise RAP in asphalt mixes has been available for some time, with a range of asphalt plant manufacturers in the US and Europe having developed a number of solutions. However, take-up of this technology has varied, with the US pushing ahead with the use of RAP while progress ha