HA dismantles footbridge over M5 in England

Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England. The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane. The dismantling and removal of the
January 3, 2013 Read time: 2 mins

Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England.

The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane.

The dismantling and removal of the 220tonne bridge required the M5 being closed in both directions for the duration of the work, from 7pm on Saturday 10 November until around 8am the following morning, when both carriageways were fully opened.
The bridge was dismantled into two sections, each of which was hoisted and removed by cranes. This method of removal was required to avoid excessive vibration due to the presence of a pipeline on the northbound carriageway.

The new pedestrian bridge is planned to be in place and available for use by early 2013.

2309 Highways Agency project manager Paul Unwin said: “The removal of the old bridge is an essential part of the managed motorway scheme, and the closures meant that our workers were able to concentrate on doing a fantastic job in dismantling the structure as quickly and as safely as possible.”

Once completed, the €109.72 million (£88mn) managed motorway scheme will cut congestion, make journey times more reliable and improve safety through the use of variable mandatory speed limits and by opening the hard shoulder as an extra running lane. 

For more information on companies in this article

Related Content

  • KIT to study bridge vibration data
    July 7, 2025
    In Germany, the Karlsruhe Institute of Technology, KIT, will use acceleration sensors to gather vibration data from bridges to pinpoint structural degradation.
  • Work underway on major UK road widening scheme
    January 14, 2013
    Work on a major US$241.9 million (£150m) road widening scheme in the East Midlands region of England has started near Nottingham. The works will focus on an 11.26km (seven mile) stretch of the A453 between M1 Junction 24 and the A52 Nottingham Ring Road – a major link serving Nottingham, the M1 and East Midlands Airport.
  • JCB excavators JS220 and 370 work close to home
    May 14, 2018
    A fleet of JCB excavators is playing a major role in a road construction project only metres from the factory where they were built. Derbyshire-based earthmoving specialist JC Balls is working for a Carillion-Tarmac joint venture on the A50 Growth Corridor Project A. The contract is part of the National Infrastructure Plan and consists of constructing a grade-separated junction on the A50 dual carriageway to the west of the town of Uttoxeter. Project managed by Amey, the scheme is creating three new
  • Romania’s important bridge project
    October 5, 2022
    Romania’s important Braila Bridge project will deliver a key crossing spanning the Danube River