Renfrew Bridge opening tests complete

The 184m-long cable-stay bridge near Glasgow, Scotland, will be the first road bridge across the River Clyde to open for passing ships.
By David Arminas August 28, 2024 Read time: 2 mins
The cable stay system is similar to Scotland’s Queensferry Crossing bridge - a twin-leaf design with each leaf opening and closing horizontally (image courtesy Graham Construction)

The first operational working of the Renfrew Bridge near Glasgow, Scotland has been accomplished ahead of the bridge opening by the end of this year.

Main contractor Graham said it will continue commissioning works for the bridge that will be the first road bridge across the River Clyde to open for passing ships. The 184m-long cable-stay two-lane road bridge will carry vehicles, pedestrians and cyclists between Glasgow and West Dunbartonshire.

The cable stay system is similar to the Queensferry Crossing - a twin-leaf design with each leaf opening and closing horizontally. Most commercial ships travel on the river during high tide, which happens once during the day and once during the night. When this happens, the bridge will be closed to road traffic, with signs nearby and information online providing advance notice of any closure to all people to plan ahead.

There will be new walking and cycling routes alongside all new roads through Renfrew and across the bridge.

The bridge is central to the major Clyde Waterfront and Renfrew Riverside redevelopment. “It was great to see the bridge closing for the first time in such a smooth, controlled and seamless operation,” said Jim Armour, project director at Graham, a privately-owned national construction company with a €1.32 billion turnover.

The two sections of the bridge were manufactured in the Netherlands and barged over, passing up the English Channel and then up the Irish sea to the site earlier this year.

The project is jointly funded by the UK and Scottish governments through the €1.32 billion Glasgow City Region, a partnership of eight councils working together.

For more information on companies in this article

Related Content

  • IRF Geneva strengthens partnership with World Bank on SuM4All Initiative
    May 1, 2018
    With the signing of the Consortium Charter in Washington DC last January, IRF Geneva has formalised its involvement in the Sustainable Mobility for All Initiative (SuM4All) Led by the World Bank, the SuM4All is a multi-stakeholder partnership that aims to reshape the global mobility agenda through advocacy, action, and financing. SuM4All brings together a diverse and high-level group of stakeholders which includes: Multilateral Developments Banks, United Nations Agencies, Programs, and Regional Commissio
  • “Structurally deficient” US bridges need warning signs, says ARTBA
    April 10, 2015
    A US construction sector group wants warning signs to be posted on bridges designated “structurally deficient" and in need of repair by state engineers. More than 61,000 structurally deficient bridges remain in need of significant repair, according to the American Road & Transportation Builders Association (ARTBA), which analysed the US Department of Transport’s National Bridge Inventory database. However, by the end of 2014 there were more than 2,000 fewer structurally deficient structures than in 20
  • Messina Strait bridge study complete
    April 6, 2023
    The Messina Strait bridge study has been completed.
  • Fehmarn Belt Tunnel opening set for mid-2029
    August 16, 2024
    Around 1,500 tonnes of reinforcement for casting the concrete tunnel elements are produced weekly for the 17.6km Fehmarn Belt Tunnel that will connect the Danish island of Lolland with the German island of Fehmarn.