PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów. Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met. Twelve pairs of piers support the two carriageways of the new motorw
July 20, 2012 Read time: 2 mins
298 PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów.

Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's  concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met.

Twelve pairs of piers support the two carriageways of the new motorway bridge, each of which is 13m wide. Falsework carried the formwork for the hollow box superstructure of the foreland bridges - consisting of girder wall formwork elements and high load-bearing GT 24 lattice girders. Depending on the support height and load different PERI shoring was used, including ST 100 stacking towers as well as shoring towers on the basis of frame-connected MULTIPROP slab props.

Meanwhile, the near 210m long section between the seventh and the 10th piers was achieved in 48 casting segments using the balanced cantilevered method. For this, contractors 4761 Dragados used four cantilever construction units based on VARIOKIT.

For more information on companies in this article

Related Content

  • Off-site monitoring with COMMAND Center
    February 19, 2021
    Transtec has also released the COMMAND Center Cloud, a sharing platform for system users.
  • Tender process underway for Polish road projects
    August 18, 2014
    The tender process is underway for two major projects in Poland. One project involves constructing three sections of the new southern ring road around Polish capital Warsaw. Building the 18.5km stretch that comprises the three sections is expected to cost in the region of €1.6 billion. The Polish General Directorate for National Roads and Motorways (GDDKiA) says that bids have to be submitted by 10th October 2014. The A section will be some 4.6km long, the B section 6.45km long, whilst the C section will be
  • Recycling used for German road expansion project
    April 20, 2018
    A milling machine from Bomag has been carrying out an important portion of the work needed for a four-lane expansion of a busy route in Southern Germany Widening work has been carried out on the B85 route from Amberg to Pittersberg in Bavaria to boost its capacity. The 2.6km section was prioritised as being in urgent need of improvement by the Federal transport Ministry. Construction work commenced in mid-2017, starting with preparation works and the project includes a cloverleaf interchange to connect t
  • Road repairs take to the air
    November 29, 2018
    Automated road repairs using 3D printing could save money and reduce disruption, reports Kristina Smith It’s the middle of the night and in the street below a team is busy carrying out repairs to the road surface. But there isn’t a human in sight. A road-repair drone has landed at the site of a crack and a 3D asphalt printer is now busy filling in that crack. A group of traffic cone drones have positioned themselves around the repair location to protect the repair drone and divert traffic around it.