Polish debut

PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów. Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met. Twelve pairs of piers support the two carriageways of the new motorw
July 20, 2012 Read time: 2 mins
298 PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów.

Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's  concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met.

Twelve pairs of piers support the two carriageways of the new motorway bridge, each of which is 13m wide. Falsework carried the formwork for the hollow box superstructure of the foreland bridges - consisting of girder wall formwork elements and high load-bearing GT 24 lattice girders. Depending on the support height and load different PERI shoring was used, including ST 100 stacking towers as well as shoring towers on the basis of frame-connected MULTIPROP slab props.

Meanwhile, the near 210m long section between the seventh and the 10th piers was achieved in 48 casting segments using the balanced cantilevered method. For this, contractors 4761 Dragados used four cantilever construction units based on VARIOKIT.

For more information on companies in this article

Related Content

  • Concrete paving developments boosting performance
    April 12, 2018
    Change is afoot at Miller Formless following its change of ownership, with investment in research and design a priority – Mike Woof writes Miller Formless is undergoing a process of change under its new ownership, with investment in the factory as well as in the product range. The recent tie-up between Guntert & Zimmerman and Miller Formless has brought additional global manufacturing capacity. Guntert & Zimmerman had established a manufacturing presence in India through an agreement with a local firm, a
  • Solid ground
    June 1, 2022
    The depth effect of heavy single drum rollers is remarkable and is significantly increased by the polygonal drum, available only from BOMAG.
  • TensarTech supports Polish contract
    November 12, 2012
    TensarTech soil retaining walls have been used during the construction of a section of the A1 motorway in Poland. Extensive underground mining in the south of the country posed a significant challenge to building the 16km Piekary Slaskie to Pyrzowice (Katowice Airport) stretch of the motorway which, on completion, will run more than 240km from Gdansk in northern Poland to Gorzyczki on the Polish-Czech Republic border. To accommodate potential differences in settlement on embankments approaching a series of
  • Trends in asphalt plant innovations
    August 27, 2019
    Key trends exist in the asphalt plant market, with manufacturers focussing on meeting customer needs and industry trends