Cranes coming down on Gordie Howe Bridge

The Gordie Howe International Bridge will route traffic away from more populated areas and directly connect Highway 401 in the Canadian province of Ontario with the Interstate 75 in the US state of Michigan.
By David Arminas June 30, 2025 Read time: 3 mins
Throughout construction of the CAN$6.4 billion bridge, the two tower cranes lifted heavy materials such as rebar, formwork, anchor boxes and all 216 stay cables (image courtesy of WDBA)

After five years, the second of two tower cranes on either side of the Gordie Howe International Bridge across the Detroit River is coming down.

The complete dismantling of the second crane, on the US end of the bridge, is expected in the next several weeks. A 600-tonne crawler crane that is fitted with a 165m-long boom is assisting in the work. An identical crane on the Canadian side was dismantled in May.

According to the Windsor-Detroit Bridge Authority, the cranes arrived on site in 2020 in an assembly process that took 35 hours over three days. They climbed in height throughout construction to keep up with the growing bridge towers in a process known as “tower crane self-climbing”. With the bridge towers reaching their full heights of 220m last year, the tower cranes, too, hit their final heights of 243m.

Throughout construction of the CAN$6.4 billion bridge, the tower cranes were used to lift heavy materials such as rebar, formwork, anchor boxes and all 216 stay cables.

Meanwhile, work continues on installation of electrical, drainage and fire suppression systems as well as barriers, signage, lighting pavement markings and the completion of a multi-use path.

The bridge is named after Gordie Howe, a professional Canadian ice hockey player who played most of his National Hockey League career with the Detroit Red Wings.

Last summer, the 26m gap was closed between the two deck of the bridge that will connect city of Detroit in the US state of Michigan and the city of Windsor in the Canadian province of Ontario. The bridge is expected to open to traffic by the end of this year. It will also include a one-lane 2.5km-long multi-use path that will accommodate two-way pedestrian and cyclist traffic and connect into existing local trail networks on both sides of the border.

The 853m main bridge deck between the two towers makes it the longest main span of any cable-stayed bridge in North America and the tenth longest in the world. Clearance above the river is 42m. It will also be the longest composite steel and concrete bridge deck for any cable-stayed bridge in the world.

The Windsor-Detroit Bridge Authority is a not-for-profit corporation wholly owned by the government of Canada  which is paying for the entire project through a public-private partnership. WDBA is responsible for the delivery of the Bridge and also responsible for project oversight of the construction and the operation of the new crossing. As the operator of the new bridge, WDBA will set and collect all tolls.

Related Content

  • Teledyne has the Çanakkale Bridge in sight
    August 12, 2022
    Teledyne FLIR’s incident detection cameras cover the entire length of the 4.6km bridge, part of Turkey’s Malkara-Çanakkale Motorway.
  • Launch soon for the Sunderland Bridge’s deck across the Wear
    March 24, 2017
    The team constructing the New Wear Crossing near the English city of Sunderland is preparing for the final launch of the 300m bridge deck. In recent weeks, the legs of the 100m-tall centrepiece have been secured to the foundations within the riverbed and most of the rigging used to raise it into place has been removed. While the bridge deck was being painted, the bottoms of both pylon legs were filled with 175tonnes of concrete, The next major process will be to slowly pull the bridge deck out acr
  • UK: Work starts on Mersey Gateway main bridge deck
    June 2, 2016
    Work has started on 2.2km Mersey Gateway’s main bridge deck as the project enters its third year of construction. The new six-lane toll bridge will link the English towns of Runcorn and Widnes and teams will begin to connect the steel support cables to the deck and upper pylons this summer. Trinity, the project’s movable scaffolding system (MSS), has cast the first 250m of the north approach viaduct and a new MSS is on its way to Halton to build the south approach viaduct. The local road network is al
  • Temporary bridge replacement in the US
    July 2, 2019
    A temporary bridge structure provided by Acrow Bridge is maintaining traffic flow for a key crossing in Vermont. The bascule bridge is allowing both vehicular and vessel traffic to pass during the reconstruction work to the North Hero-Grand Isle Drawbridge in Vermont. The US$60 million project involves replacing the historic twin leaf bascule bridge on Lake Champlain. This modular steel bascule bridge is allowing transport to continue to and from the Lake Champlain island towns of North Hero and Grand Isl