South Africa's world class tollway development

Part of an extensive motorway network measuring some 185km, the ongoing Gauteng Freeway Improvement Project (GIFP) is creating a modern, world-class toll route system that provides major impetus to socio-economic growth in South Africa's most populous and commercially active region.
May 8, 2012 Read time: 2 mins
Part of an extensive motorway network measuring some 185km, the ongoing Gauteng Freeway Improvement Project (GIFP) is creating a modern, world-class toll route system that provides major impetus to socio-economic growth in South Africa's most populous and commercially active region.

Being implemented in stages by the 3156 South African National Road Agency (SANRAL), these routes radiate outwards from the country's largest city Johannesburg to Pretoria's industrial and residential centres and to all points of the compass.

Already on major N1 and N3 transportation upgrades within Gauteng, previous congestion has now been replaced by free-flowing traffic that is foremost driven by business priorities that are time dependant. So too are the ensuing construction works.

National Route 12 (N12) is one of SANRAL's strategic priorities and it is here that civil engineering contractor 3038 Raubex Construction is  implementing a ACTFILE LOCATION:

• South Africa
PROJECT:
• National Route 12 (N12)
CONTRACTOR:
• Raubex Construction
EQUIPMENT:
178 Caterpillar RM500 rotary mixer
complete  overhaul on Section 19, an intensive programme running over 30 months.

Three major new interchanges, successive bridge widenings and an east and westbound three-lane highway in either direction will replace the existing N12 dual carriageway system along approximately 10km between the current Tom Jones and Daveyton on- and off-ramps.

The median reserve will be replaced by a central concrete median barrier to make room for the new lanes, which is where the roadworks begin, progressively moving from the inside out to complete the new freeway system.

This is the main access point passing into and out of Gauteng's West Rand region to the agricultural and mining heartland of Mpumalanga province.

Managing high traffic densities together with major road realignments will be just one of a number of challenges that need to be carefully managed. The N12 design calls for an emulsion and cement stabilisation mix for the sub-base layers.

"The N12 contract follows a similar pattern to the SANRAL project we completed in May 2010 for Section 1 of the R21 upgrade, which links OR Tambo International Airport with Pretoria [South Africa's capital]," explains Raubex Construction operations manager, Wouter van der Merwe.

For more information on companies in this article

Related Content

  • Producing recycled materials at an airport for surface use
    October 1, 2018
    Recycling of materials has been carried out at Cologne/Bonn Airport in a move to boost efficiency Using the Wirtgen KMA 220 mobile cold recycling mixing plant allows road construction materials to be recycled or upgraded onsite and avoids the need for numerous transport trips. The system is also economical, as became clear from a job at Cologne/Bonn airport at the end of 2017. There the plant, located immediately next to the job site, produced around 11,000tonnes of materials for a hydraulically bound ba
  • Qatar developing highway expansion plan
    June 16, 2016
    Qatar is setting the wheels in motion for the development of a comprehensive highway network. Engineering firm KBR is working on a three year, US$185 million consultancy contract to manage Qatar’s highway construction and improvement programme. This package is an extension to KBR’s earlier contract, which the firm won in 2010. The new contract was awarded by Qatar’s Public Works Authority (Ashghal) and the highway network plans will form part of the country’s National Vision 2030 strategy. New and improved
  • $10.1 billion South Australia road and tunnel project
    July 14, 2025
    Work is underway for a $10.1 billion South Australian road and tunnel project.
  • Kosovan highway ahead of schedule
    April 25, 2012
    In Kosovo, work is pushing ahead of schedule on the Route 7 highway to link capital Pristina with the Albanian border. Sections of the 120km highway have been opened, one year ahead of schedule. An official opening of several sections of the highway has been carried out by Kosovan leaders, including Prime Minister Hashim Thaçi, President Atifete Jahjaga, and members of Parliament, along with Albanian Prime Minister Sali Berisha and US representatives Eliot Engel (D- NY) and Gary Peters (D-MI) joined thousan