Pressure is on Superslim formwork

Temporary works specialist Altrad RMD Kwikform - Altrad RMDK - is helping realign the A452 road over a new rail line for England’s future high-speed trains.
By David Arminas February 4, 2025 Read time: 3 mins
Superslim Soldiers are designed to handle high loads, which for the A452 realignment project, ensured that the formwork would remain stable under the pressure of the concrete (image courtesy Altrad RMD Kwikform)

 

Altrad RMDK is working with HS2’s construction partner for the Midlands region, Balfour Beatty VINCI (BBV), and civil engineering and groundworks contractor Galldris. The A452 Kenilworth Road Overbridge is a fully integral box structure with in-situ concrete base, abutments and wingwalls, spanning more than 76m. The project is part of the vast HS2 landscape realignment of the trunk A452 road over the new high speed rail line.

The structure was one of the highest concrete pours undertaken by Altrad RMDK in Europe to date with a pouring height of 13.5m to one of the main wingwalls. The project’s success was critical in maintaining the momentum of the HS2 timeline, highlighting the collaborative efforts of all involved.

The project presented a multitude of challenges due to the complex shape and weight of the bridge. One of the main challenges was overcoming the complex geometric patterns used for the wingwalls. These wingwalls tapered in height along their length and also along their width across the base. Not only this, but the external shutters lean into the internal face to taper in width across the height.

Where the wingwalls met the abutment walls, there was a complex movement joint that was required to allow for the expansion of the respective elements while still retaining the backfill that would eventually encapsulate the structure. The project demanded meticulous planning, coordination, and execution, with the additional pressure of adhering to a tight schedule.

Altrad RMDK and Galldris worked in partnership, bringing together expertise and resources from both organisations, which proved instrumental in overcoming the complex challenges posed by the project’s scope.

The contractor needed a solution that could be configured into various shapes and sizes. The solution was a custom specification to be engineered using Superslim Soldiers and Alform Aluminium Beams to meet the complex requirements.

Superslim Soldiers are designed to handle high loads, making them an ideal solution for a pour of this stature; they ensured that the formwork would remain stable under the pressure of the concrete. The beams helped maintain the structure’s shape and integrity during the entire pouring process, which was crucial in order to prevent deformities and ensure the accurate formation.

The Alform Beams provided a quick, durable and lightweight solution, allowing for simple installation, which was particularly advantageous on this high pour as moving and positioning formwork can be time and labour intensive.

Despite being lightweight, Alform Beams withstood the substantial pressure from the concrete. They worked alongside Superslim Soliders to ensure that formwork remained intact and stable throughout the pour. This was important as it was essential that the solutions maintained the tapering shapes and dimensions of the wingwalls throughout the pouring process.

“The A452 Kenilworth Overbridge project highlights Altrad RMD Kwikform’s engineering capabilities and innovative solutions,” said Stuart Grant, senior sales representative at Altrad RMD Kwikform. “Through partnerships, careful planning and the use of advanced equipment, the project demonstrated the effective collaboration needed for this infrastructure development.”

Altrad RMD Kwikform provides of formwork, falsework/shoring, heavy-duty support, ground shoring and safety and access systems, specialising in temporary structure needed to deliver major infrastructure and building projects. The company designs, hires and sells formwork, falsework/shoring, heavy-duty support, ground shoring as well as safety and access systems.

Key sectors include civil engineering and infrastructure, ground works, energy and industrial, commercial and multi-storey residential buildings. The company works in 3D designs and BIM (building information modelling)-compliant models through its visualisation software LocusEye.

 

Related Content

  • Futureproofing UK construction equipment resilience
    May 5, 2021
    Rob Oliver is the longstanding CEO of the Construction Equipment Association (CEA), the UK trade association for the UK construction equipment industry. Guy Woodford recently caught up with him to discuss the industry’s health and the key issues facing the CEA and its members in 2021 and beyond.
  • Efficient aggregate production with new technology
    December 9, 2022
    New equipment is providing major benefits for aggregate production, offering superior product quality as well as increased throughput, while also being able to better meet sustainability targets for customers
  • First deck span completed for Mersey Gateway's north approach viaduct
    April 4, 2016
    The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. Work started on site in May 2014 to build a six-lane toll bridge over the Mersey River between the towns of Runcorn and Widnes and opening is set for the autumn of 2017. As well as construction of the new bridge, works include the upgrading of 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of tra
  • Kijlstra’s headwalls are coming up smelling of Roses
    January 3, 2013
    More than 100 of Kijlstra’s precast concrete headwalls are being used on a trunk road improvement in South West Wales. They were said to be chosen are being used on Welsh Government’s €69.72 million (£56.7mn) St Clears to Red Roses upgrade for their eco-friendly, health and safety and time/cost/waste saving benefits. The standard Type 1 headwalls are being installed by main contractor SRB Civil Engineering (a joint venture between Roadbridge and John Sisk & Son). They are being connected to both concrete an