Pressure is on Superslim formwork

Temporary works specialist Altrad RMD Kwikform - Altrad RMDK - is helping realign the A452 road over a new rail line for England’s future high-speed trains.
By David Arminas February 4, 2025 Read time: 3 mins
Superslim Soldiers are designed to handle high loads, which for the A452 realignment project, ensured that the formwork would remain stable under the pressure of the concrete (image courtesy Altrad RMD Kwikform)

 

Altrad RMDK is working with HS2’s construction partner for the Midlands region, Balfour Beatty VINCI (BBV), and civil engineering and groundworks contractor Galldris. The A452 Kenilworth Road Overbridge is a fully integral box structure with in-situ concrete base, abutments and wingwalls, spanning more than 76m. The project is part of the vast HS2 landscape realignment of the trunk A452 road over the new high speed rail line.

The structure was one of the highest concrete pours undertaken by Altrad RMDK in Europe to date with a pouring height of 13.5m to one of the main wingwalls. The project’s success was critical in maintaining the momentum of the HS2 timeline, highlighting the collaborative efforts of all involved.

The project presented a multitude of challenges due to the complex shape and weight of the bridge. One of the main challenges was overcoming the complex geometric patterns used for the wingwalls. These wingwalls tapered in height along their length and also along their width across the base. Not only this, but the external shutters lean into the internal face to taper in width across the height.

Where the wingwalls met the abutment walls, there was a complex movement joint that was required to allow for the expansion of the respective elements while still retaining the backfill that would eventually encapsulate the structure. The project demanded meticulous planning, coordination, and execution, with the additional pressure of adhering to a tight schedule.

Altrad RMDK and Galldris worked in partnership, bringing together expertise and resources from both organisations, which proved instrumental in overcoming the complex challenges posed by the project’s scope.

The contractor needed a solution that could be configured into various shapes and sizes. The solution was a custom specification to be engineered using Superslim Soldiers and Alform Aluminium Beams to meet the complex requirements.

Superslim Soldiers are designed to handle high loads, making them an ideal solution for a pour of this stature; they ensured that the formwork would remain stable under the pressure of the concrete. The beams helped maintain the structure’s shape and integrity during the entire pouring process, which was crucial in order to prevent deformities and ensure the accurate formation.

The Alform Beams provided a quick, durable and lightweight solution, allowing for simple installation, which was particularly advantageous on this high pour as moving and positioning formwork can be time and labour intensive.

Despite being lightweight, Alform Beams withstood the substantial pressure from the concrete. They worked alongside Superslim Soliders to ensure that formwork remained intact and stable throughout the pour. This was important as it was essential that the solutions maintained the tapering shapes and dimensions of the wingwalls throughout the pouring process.

“The A452 Kenilworth Overbridge project highlights Altrad RMD Kwikform’s engineering capabilities and innovative solutions,” said Stuart Grant, senior sales representative at Altrad RMD Kwikform. “Through partnerships, careful planning and the use of advanced equipment, the project demonstrated the effective collaboration needed for this infrastructure development.”

Altrad RMD Kwikform provides of formwork, falsework/shoring, heavy-duty support, ground shoring and safety and access systems, specialising in temporary structure needed to deliver major infrastructure and building projects. The company designs, hires and sells formwork, falsework/shoring, heavy-duty support, ground shoring as well as safety and access systems.

Key sectors include civil engineering and infrastructure, ground works, energy and industrial, commercial and multi-storey residential buildings. The company works in 3D designs and BIM (building information modelling)-compliant models through its visualisation software LocusEye.

 

Related Content

  • Work begins on Stockholm’s new bypass
    August 22, 2016
    The first tunnels are being excavated for the huge bypass tunnel in Sweden’s capital Stockholm – Adrian Greeman writes. After years of preparation and design, blasting and rock moving for Sweden's largest infrastructure project began south of the city this year. It sets in train a decade-long project that will create a new half-ring dual three-lane motorway for the city, 20km long. With most of it deep underground, it will also be one of Europe's largest ever road tunnels. The scheme is aimed at transformin
  • New third Don River bridge project planned for Aberdeen
    August 27, 2014
    A new bridge is planned for the Scottish city of Aberdeen, centre of the country’s oil industry. Continued growth in the city from the oil industry is fuelling an increase in vehicle numbers, with congestion a serious problem. As a result, Aberdeen City Council has given a contract to Balfour Beatty to construct the Third Don Crossing at a cost of some €17.6 million (£14.3 million). The two existing crossings to the north of the city centre suffer heavy congestion at peak periods at present and this new bri
  • Sandvik’s Turkish delight at groundbreaking tunnel vision
    May 20, 2014
    Turkey’s longest, and what will be the world’s fourth longest, highway tunnel is being built under Mount Ovit in the northeast of the country. Sandvik Construction is playing a vital role in the construction of the giant new structure, which will enable all-year-round access to what is a relatively remote and often snow-blocked part of Anatolia Having had their freedom of movement blighted for many years by wintertime snow blocking the D925 highway, along with narrower roads and passes, at Mount Ovit, resi
  • Tunnels eliminate bottlenecks
    February 10, 2012
    Some of the bottlenecks on the multi-lane Mittlere Ring, Munich, Germany, one of the main arterial roads circling the city centre have been eliminated by the addition of new tunnels. The Luise-Kiesselbach Square, the last section of this road improvement effort, is an important traffic hub south-west of the city where motorways A96 from Lindau and A5 from Garmisch meet, causing long delays in daily rush-hour traffic, writes Patrick Smith.