Skip to main content

First deck span completed for Mersey Gateway's north approach viaduct

The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. Work started on site in May 2014 to build a six-lane toll bridge over the Mersey River between the towns of Runcorn and Widnes and opening is set for the autumn of 2017. As well as construction of the new bridge, works include the upgrading of 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of tra
April 4, 2016 Read time: 4 mins
First span of the north approach viaduct showing the north abutment. Photo: David Hunter
The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed.

Work started on site in May 2014 to build a six-lane toll bridge over the Mersey River between the towns of Runcorn and Widnes and opening is set for the autumn of 2017. As well as construction of the new bridge, works include the upgrading of 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of traffic uses the new bridge.

The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.

The MSS, which acts as a giant concrete mould, was specially designed for the 6126 Mersey Gateway Project. It is being used to build the two elevated approach viaducts over the Mersey estuary.

The span connects the beginning of the approach viaduct from the north abutment in Widnes to the first supporting pier. It measures around 60m long and 18m wide and is angled at 5 degrees to allow vehicles to travel safely around the curve of the approach road.
Construction teams worked around the clock to get the span ready. This involved pouring 1,146m3 of concrete into the MSS non-stop over 34 hours.

"This is a real achievement for the project and a milestone that we've been looking forward to with anticipation,” said Declan Cannar, Merseylink's general foreman in charge of the MSS operation. “We're now busy preparing the MSS so it's ready to cast the next section."

The approach viaduct deck is being constructed in three phases. The deck spans are constructed first by the MSS, then a deck slab is built on top of the span, and finally the outer deck or ‘wings' are built by a wing traveller machine to provide the full six-lane width of the approach road.

The MSS has moved to its second casting position ready for work to begin on the next span, which will be cast in March.

Meanwhile, Total Plant Hire, based in Manchester, has hired out two new Doosan DA30 30tonne articulated dump trucks (ADTs) fitted with high flotation tyres for the project.

Like all 695 Doosan ADTs, the DA30 model features an articulation hinge behind the turning ring to provide equal weight distribution to the front axle even during maximum steer articulation. This together with a free-swinging rear tandem bogie ensures equal distribution of weight to each wheel and delivers permanent six-wheel contact and drive for equal power distribution and excellent performance on difficult terrain.
The specially shaped body and sloping frame on the DA30 offers a low centre of gravity and perfect weight distribution. The Doosan machines purchase by Total Plant Hire have been equipped with high flotation tyres to further help traction in the tough working conditions.

A temporary trestle bridge has been built as an access platform for workers build the new structures in the river. Accessed from the trestle bridge, temporary cofferdams have been built to enable foundations to be laid for the three pylons that will support the main bridge. The Doosan DA30 ADTs are removing earth excavated from the cofferdams and from others across the site.

The Doosan DA30 ADTs are also being for construction of supporting piers for the elevated approach viaducts, which cross the Manchester Ship Canal and the St Helens Canal. Each approach viaduct is supported by a number of supporting, there being 20 in total. These will march across the salt marsh on either side of the estuary.

For more information on companies in this article

Related Content

  • Tunnel for Colombia’s Calarca – Cajamarca Highway
    May 23, 2014
    A new tunnel is forming an important link for a major Colombian highway - Mauro Nogarin reports Work on a major highway project is underway in Colombia, forming part of the Bogota-Buenaventura Corridor. The highway has a length of 503km and is located in central Colombia, connecting the departments of Tolima and Quindio, across the central Andes, with a total cost of around US$330 million. A key section of the project consists of building a unidirectional tunnel of approximately 8.65km in length. Anot
  • Salini Impregilo morphs into Webuild
    May 19, 2020
    The name of a major player on the international construction scene has changed.
  • South Africa bridge deals for Msikaba and Mtentu rivers by end 2016
    August 1, 2016
    The South African National Roads Agency (SANRAL) said it is on track to announce tender winners for two bridges, across the Msikaba River and Mtentu River, by the end of the year. The Msikaba River Bridge will be constructed on the N2 Wild Coast Toll Road and will consist of a cable-stayed 580m-long structure spanning a deep gorge. The Mtentu River Bridge, also on the N2 Wild Coast Toll Road and around 12km to the north of Msikaba River, is expected to be a concrete structure and nearl.y 1.2kkm long.
  • Barge-mounted Manitowoc MLC300 lists Illinois bridge into place
    June 28, 2018
    The reduced footprint and floating counterweight meant that it is much more efficient for contractors to barge-mount a crawler crane. The crane can be on smaller water-based barges because the machine automatically adjusts its centre of gravity for each lift. Kraemer North America recently used an MLC300 to help replace an 84-year-old truss bridge, the 756m Savanna-Sabula Bridge near Savanna, in the US state of Illinois. The Savanna–Sabula Bridge was a truss bridge and causeway crossing the Mississippi Ri